Sample-to-Answer Microfluidic qPCR Cartridge
Product family: Closed Molecular Multiplex Pods.
Flow: Freeze-Dried PCR Beads → COC Cleanroom Optical Mold → Lyophilized Bead Pick-Place → Laser Foil Valve Welding → Ultrasound Liquid Blister Fill → Vision Foil Integrity & Box → Hospital Microbiology Labs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. COC Cleanroom Optical Mold | 3.9 s | 35 min | 94% | 98.1% | 14,000 | 21,000 (1.50 d) | 18,656 |
| 2. Lyophilized Bead Pick-Place | 4.7 s | 25 min | 92% | 97.4% | 8,400 | 19,600 (1.40 d) | 14,966 |
| 3. Laser Foil Valve Welding | 6.2 s | 40 min | 84% | 95.2% | 7,000 | 25,200 (1.80 d) | 9,828 |
| 4. Ultrasound Liquid Blister Fill | 4.3 s | 15 min | 94% | 98.6% | 5,600 | 14,000 (1.00 d) | 16,974 |
| 5. Vision Foil Integrity & Box | 3.5 s | 10 min | 96% | 99.1% | 7,000 | 16,800 (1.20 d) | 21,691 |
Key figures
- Takt time
- 5.8 s
- Lead time
- 8.70 d
- Value-added time
- 22.6 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 88.9%
- Customer demand per day
- 14,000 units
- Line capacity per day
- 9,828 units
- Bottleneck
- Laser Foil Valve Welding
Reading the bottleneck
The bottleneck is "Laser Foil Valve Welding": it can process 9,828 units per day against a demand of 14,000 units, so it falls short of demand by 29.8%. Once downtime and scrap are counted, its cycle time grows from 6.2 s to 7.8 s, against a takt of 5.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of In-Vitro Diagnostics (IVD) & Kits: In-Vitro Diagnostics (IVD) & Kits
- Rapid Antigen / Cardiac Lateral Flow Strip Line
- Gold-Electrode Reel-to-Reel Glucose Test Strip
- CMOS Nano-Well DNA Sequencing Flow Cell
- Positive-Charged Silane Pathology Glass Slide
- Vacuum PET Blood Collection EDTA Tube Line
- Chemiluminescence CLIA Automated Reagent Pack
- Point-of-Care Blood Gas & Lactate Cartridge
- 96-Well Streptavidin Pre-Coated ELISA Plate
- Flocked Nasopharyngeal Swab & Liquid Amies
- Fluorescent Sensor Aerobic Blood Culture Bottle
- Newborn Metabolic Screening Filter Paper Card