Gold-Electrode Reel-to-Reel Glucose Test Strip
Product family: Enzyme Electrochemical Strips.
Flow: FAD-GDH Enzyme Ink → Rotary Screen Carbon/Au Ink → Laser Ablate Electrode Gap → Enzyme Slot-Die Coat & Dry → Hydrophilic Spacer Laminate → Master Reel Singulation & Vial → Pharmacy Retail Channels
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Rotary Screen Carbon/Au Ink | 1.2 s | 35 min | 94% | 98.1% | 160,000 | 240,000 (1.50 d) | 60,631 |
| 2. Laser Ablate Electrode Gap | 1.2 s | 25 min | 92% | 97.4% | 96,000 | 224,000 (1.40 d) | 58,619 |
| 3. Enzyme Slot-Die Coat & Dry | 1.2 s | 40 min | 84% | 95.2% | 80,000 | 288,000 (1.80 d) | 50,780 |
| 4. Hydrophilic Spacer Laminate | 1.2 s | 15 min | 94% | 98.6% | 64,000 | 160,000 (1.00 d) | 60,824 |
| 5. Master Reel Singulation & Vial | 1.2 s | 10 min | 96% | 99.1% | 80,000 | 192,000 (1.20 d) | 63,265 |
Key figures
- Takt time
- 0.5 s
- Lead time
- 8.70 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 88.9%
- Customer demand per day
- 160,000 units
- Line capacity per day
- 50,780 units
- Bottleneck
- Enzyme Slot-Die Coat & Dry
Reading the bottleneck
The bottleneck is "Enzyme Slot-Die Coat & Dry": it can process 50,780 units per day against a demand of 160,000 units, so it falls short of demand by 68.3%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of In-Vitro Diagnostics (IVD) & Kits: In-Vitro Diagnostics (IVD) & Kits
- Rapid Antigen / Cardiac Lateral Flow Strip Line
- Sample-to-Answer Microfluidic qPCR Cartridge
- CMOS Nano-Well DNA Sequencing Flow Cell
- Positive-Charged Silane Pathology Glass Slide
- Vacuum PET Blood Collection EDTA Tube Line
- Chemiluminescence CLIA Automated Reagent Pack
- Point-of-Care Blood Gas & Lactate Cartridge
- 96-Well Streptavidin Pre-Coated ELISA Plate
- Flocked Nasopharyngeal Swab & Liquid Amies
- Fluorescent Sensor Aerobic Blood Culture Bottle
- Newborn Metabolic Screening Filter Paper Card