Rapid Antigen / Cardiac Lateral Flow Strip Line
Product family: Nitrocellulose POCT Cassettes.
Flow: Nitrocellulose Membrane Supplier → Precision Conjugate Dispense → 37°C Low-RH Laminate Cure → High-Speed Reel Strip Slit → Cassette Snap & Vision QR → N2 Foil Pouch & QC Panel → Hospital & Retail POCT
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Precision Conjugate Dispense | 1.2 s | 35 min | 94% | 98.1% | 85,000 | 127,500 (1.50 d) | 60,631 |
| 2. 37°C Low-RH Laminate Cure | 1.2 s | 25 min | 92% | 97.4% | 51,000 | 119,000 (1.40 d) | 58,619 |
| 3. High-Speed Reel Strip Slit | 1.2 s | 40 min | 84% | 95.2% | 42,500 | 153,000 (1.80 d) | 50,780 |
| 4. Cassette Snap & Vision QR | 1.2 s | 15 min | 94% | 98.6% | 34,000 | 85,000 (1.00 d) | 60,824 |
| 5. N2 Foil Pouch & QC Panel | 1.2 s | 10 min | 96% | 99.1% | 42,500 | 102,000 (1.20 d) | 63,265 |
Key figures
- Takt time
- 1.0 s
- Lead time
- 8.70 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 88.9%
- Customer demand per day
- 85,000 units
- Line capacity per day
- 50,780 units
- Bottleneck
- High-Speed Reel Strip Slit
Reading the bottleneck
The bottleneck is "High-Speed Reel Strip Slit": it can process 50,780 units per day against a demand of 85,000 units, so it falls short of demand by 40.3%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 1.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of In-Vitro Diagnostics (IVD) & Kits: In-Vitro Diagnostics (IVD) & Kits
- Sample-to-Answer Microfluidic qPCR Cartridge
- Gold-Electrode Reel-to-Reel Glucose Test Strip
- CMOS Nano-Well DNA Sequencing Flow Cell
- Positive-Charged Silane Pathology Glass Slide
- Vacuum PET Blood Collection EDTA Tube Line
- Chemiluminescence CLIA Automated Reagent Pack
- Point-of-Care Blood Gas & Lactate Cartridge
- 96-Well Streptavidin Pre-Coated ELISA Plate
- Flocked Nasopharyngeal Swab & Liquid Amies
- Fluorescent Sensor Aerobic Blood Culture Bottle
- Newborn Metabolic Screening Filter Paper Card