Vacuum PET Blood Collection EDTA Tube Line
Product family: Spray-Coated Clot & EDTA Tubes.
Flow: Medical PET & Bromobutyl → 48-Cavity Medical PET Mold → Micro-Mist K2EDTA Spray Dry → Rubber Stopper Vacuum Evac → Color-Coded Tube Cap → Vacuum Draw & Label Serialize → Clinical Blood Labs Worldwide
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 48-Cavity Medical PET Mold | 1.2 s | 35 min | 94% | 98.1% | 90,000 | 135,000 (1.50 d) | 60,631 |
| 2. Micro-Mist K2EDTA Spray Dry | 1.2 s | 25 min | 92% | 97.4% | 54,000 | 126,000 (1.40 d) | 58,619 |
| 3. Rubber Stopper Vacuum Evac | 1.2 s | 40 min | 84% | 95.2% | 45,000 | 162,000 (1.80 d) | 50,780 |
| 4. Color-Coded Tube Cap | 1.2 s | 15 min | 94% | 98.6% | 36,000 | 90,000 (1.00 d) | 60,824 |
| 5. Vacuum Draw & Label Serialize | 1.2 s | 10 min | 96% | 99.1% | 45,000 | 108,000 (1.20 d) | 63,265 |
Key figures
- Takt time
- 0.9 s
- Lead time
- 8.70 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 88.9%
- Customer demand per day
- 90,000 samples
- Line capacity per day
- 50,780 samples
- Bottleneck
- Rubber Stopper Vacuum Evac
Reading the bottleneck
The bottleneck is "Rubber Stopper Vacuum Evac": it can process 50,780 samples per day against a demand of 90,000 samples, so it falls short of demand by 43.6%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of In-Vitro Diagnostics (IVD) & Kits: In-Vitro Diagnostics (IVD) & Kits
- Rapid Antigen / Cardiac Lateral Flow Strip Line
- Sample-to-Answer Microfluidic qPCR Cartridge
- Gold-Electrode Reel-to-Reel Glucose Test Strip
- CMOS Nano-Well DNA Sequencing Flow Cell
- Positive-Charged Silane Pathology Glass Slide
- Chemiluminescence CLIA Automated Reagent Pack
- Point-of-Care Blood Gas & Lactate Cartridge
- 96-Well Streptavidin Pre-Coated ELISA Plate
- Flocked Nasopharyngeal Swab & Liquid Amies
- Fluorescent Sensor Aerobic Blood Culture Bottle
- Newborn Metabolic Screening Filter Paper Card