CMOS Nano-Well DNA Sequencing Flow Cell
Product family: High-Throughput NGS Flow Cells.
Flow: Glass & Silicon Bio-Chips → CMOS Bio-Wafer Silanization → Microfluidic Glass Etch Bond → Oligo Surface Lawn Grafting → Cold Fluidic Manifold Leak → Fluorescence QC & Cold Foil → Genomic Research Centers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. CMOS Bio-Wafer Silanization | 56.0 s | 35 min | 94% | 98.1% | 650 | 975 (1.50 d) | 855 |
| 2. Microfluidic Glass Etch Bond | 68.0 s | 25 min | 92% | 97.4% | 390 | 910 (1.40 d) | 679 |
| 3. Oligo Surface Lawn Grafting | 89.0 s | 40 min | 84% | 95.2% | 325 | 1,170 (1.80 d) | 442 |
| 4. Cold Fluidic Manifold Leak | 61.0 s | 15 min | 94% | 98.6% | 260 | 650 (1.00 d) | 786 |
| 5. Fluorescence QC & Cold Foil | 50.0 s | 10 min | 96% | 99.1% | 325 | 780 (1.20 d) | 1,005 |
Key figures
- Takt time
- 83.1 s
- Lead time
- 8.71 d
- Value-added time
- 324 s
- Process cycle efficiency (PCE)
- 0.069%
- Rolled throughput yield (RTY)
- 88.9%
- Customer demand per day
- 650 units
- Line capacity per day
- 442 units
- Bottleneck
- Oligo Surface Lawn Grafting
Reading the bottleneck
The bottleneck is "Oligo Surface Lawn Grafting": it can process 442 units per day against a demand of 650 units, so it falls short of demand by 32.0%. Once downtime and scrap are counted, its cycle time grows from 89.0 s to 111 s, against a takt of 83.1 s. The largest loss at this step is equipment downtime (uptime 84%), about 17.0 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of In-Vitro Diagnostics (IVD) & Kits: In-Vitro Diagnostics (IVD) & Kits
- Rapid Antigen / Cardiac Lateral Flow Strip Line
- Sample-to-Answer Microfluidic qPCR Cartridge
- Gold-Electrode Reel-to-Reel Glucose Test Strip
- Positive-Charged Silane Pathology Glass Slide
- Vacuum PET Blood Collection EDTA Tube Line
- Chemiluminescence CLIA Automated Reagent Pack
- Point-of-Care Blood Gas & Lactate Cartridge
- 96-Well Streptavidin Pre-Coated ELISA Plate
- Flocked Nasopharyngeal Swab & Liquid Amies
- Fluorescent Sensor Aerobic Blood Culture Bottle
- Newborn Metabolic Screening Filter Paper Card