Dual-Release Fixed-Dose Bilayer Tablet

Product family: Immediate + Extended Layer Tabs.

Flow: Sustained-Release Matrix Supplier → Dual Blend Prep & Sieve → Pre-Compress Layer 1 Turret → Layer 2 Feed & Main Tamp → Layer-Separation Stress QC → Cold-Form Blister & FMD Box → Chronic Metabolic Care

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Dual-Release Fixed-Dose Bilayer TabletSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Sustained-Release Matrix Supplier → Dual Blend Prep & Sieve (1.2 s) → Pre-Compress Layer 1 Turret (1.2 s) → Layer 2 Feed & Main Tamp (1.2 s) → Layer-Separation Stress QC (1.2 s) → Cold-Form Blister & FMD Box (1.2 s) → Chronic Metabolic Care.SUPPLIERSustained-ReleaseMatrix SupplierI1.60 d1Dual Blend Prep &SieveC/T 1.2 sI1.80 d2Pre-CompressLayer 1 TurretC/T 1.2 sI2.10 d3Layer 2 Feed &Main TampC/T 1.2 sI1.20 d4Layer-SeparationStress QCC/T 1.2 sI1.40 d5Cold-Form Blister& FMD BoxC/T 1.2 sI1.80 dCUSTOMERChronicMetabolic Care110,000 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Dual Blend Prep & Sieve1.2 s45 min94%99.1%165,000176,000 (1.60 d)40,522
2. Pre-Compress Layer 1 Turret1.2 s75 min89%97.6%165,000198,000 (1.80 d)36,917
3. Layer 2 Feed & Main Tamp1.2 s65 min84%96.1%165,000231,000 (2.10 d)34,577
4. Layer-Separation Stress QC1.2 s35 min91%98.2%88,000132,000 (1.20 d)38,258
5. Cold-Form Blister & FMD Box1.2 s15 min95%99.4%55,000154,000 (1.40 d)41,077

Key figures

Takt time
0.5 s
Lead time
9.90 d
Value-added time
6.0 s
Process cycle efficiency (PCE)
0.001%
Rolled throughput yield (RTY)
90.7%
Customer demand per day
110,000 units
Line capacity per day
34,577 units
Bottleneck
Layer 2 Feed & Main Tamp

Reading the bottleneck

The bottleneck is "Layer 2 Feed & Main Tamp": it can process 34,577 units per day against a demand of 110,000 units, so it falls short of demand by 68.6%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.