High-Shear Granulation & Film-Coated Tablet
Product family: Cardiovascular Chronic Tabs.
Flow: Excipient Suppliers → Weigh, Sieve & High-Shear Wet → Fluid-Bed Dry & Mill Blend → 90-Station Rotary Compression → Aqueous Pan Film Coating → Blister, Leaflet & Case Pack → Retail Pharmacy Wholesalers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Weigh, Sieve & High-Shear Wet | 1.2 s | 45 min | 94% | 99.1% | 360,000 | 384,000 (1.60 d) | 61,482 |
| 2. Fluid-Bed Dry & Mill Blend | 1.2 s | 75 min | 89% | 97.6% | 360,000 | 432,000 (1.80 d) | 56,462 |
| 3. 90-Station Rotary Compression | 1.2 s | 65 min | 84% | 96.1% | 360,000 | 504,000 (2.10 d) | 52,740 |
| 4. Aqueous Pan Film Coating | 1.2 s | 35 min | 91% | 98.2% | 192,000 | 288,000 (1.20 d) | 58,365 |
| 5. Blister, Leaflet & Case Pack | 1.2 s | 15 min | 95% | 99.4% | 120,000 | 336,000 (1.40 d) | 62,324 |
Key figures
- Takt time
- 0.3 s
- Lead time
- 9.90 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 240,000 units
- Line capacity per day
- 52,740 units
- Bottleneck
- 90-Station Rotary Compression
Reading the bottleneck
The bottleneck is "90-Station Rotary Compression": it can process 52,740 units per day against a demand of 240,000 units, so it falls short of demand by 78.0%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oral Solid Dose, Tablets & Blister: Oral Solid Dose, Tablets & Blister
- High-Speed ALU-ALU Tropicalized Blister Line
- Enteric Pellet Hard-Gelatin Capsule Filling
- RH<12% Low-Humidity Effervescent Tube Line
- Oral Suspension Syrup & Child-Safe Cap Line
- OEB-5 High-Potency Contained Oncology Tablet
- Rotary Die Liquid-Fill Softgel Vitamin Line
- 4-Lane Aluminum Foil Stick-Pack Powder Line
- Thin-Film Orally Disintegrating Strip Line
- Dual-Release Fixed-Dose Bilayer Tablet
- Randomized Double-Blind Clinical Trial Kit Pack
- Continuous Melt-Pour Suppository PVC Shell