Oral Suspension Syrup & Child-Safe Cap Line

Product family: 120mL Antibiotic Dry Powder.

Flow: Amber Glass Bottle Supplier → Dry Double-Cone Blending → Auger Powder Dosing Fill → CRC Child-Resistant Cap Seal → Dose Cup Snap & Leaflets → Case Checkweigh & Serialization → Pediatric Pharmacies

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Oral Suspension Syrup & Child-Safe Cap LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Amber Glass Bottle Supplier → Dry Double-Cone Blending (2.4 s) → Auger Powder Dosing Fill (2.8 s) → CRC Child-Resistant Cap Seal (3.6 s) → Dose Cup Snap & Leaflets (2.6 s) → Case Checkweigh & Serialization (2.1 s) → Pediatric Pharmacies.SUPPLIERAmber GlassBottle SupplierI1.60 d1Dry Double-ConeBlendingC/T 2.4 sI1.80 d2Auger PowderDosing FillC/T 2.8 sI2.10 d3CRCChild-Resistant…C/T 3.6 sI1.20 d4Dose Cup Snap &LeafletsC/T 2.6 sI1.40 d5Case Checkweigh &SerializationC/T 2.1 sI1.80 dCUSTOMERPediatricPharmacies16,000 / vials

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Dry Double-Cone Blending2.4 s45 min94%99.1%24,00025,600 (1.60 d)20,261
2. Auger Powder Dosing Fill2.8 s75 min89%97.6%24,00028,800 (1.80 d)15,822
3. CRC Child-Resistant Cap Seal3.6 s65 min84%96.1%24,00033,600 (2.10 d)11,526
4. Dose Cup Snap & Leaflets2.6 s35 min91%98.2%12,80019,200 (1.20 d)17,658
5. Case Checkweigh & Serialization2.1 s15 min95%99.4%8,00022,400 (1.40 d)23,473

Key figures

Takt time
3.4 s
Lead time
9.90 d
Value-added time
13.5 s
Process cycle efficiency (PCE)
0.003%
Rolled throughput yield (RTY)
90.7%
Customer demand per day
16,000 vials
Line capacity per day
11,526 vials
Bottleneck
CRC Child-Resistant Cap Seal

Reading the bottleneck

The bottleneck is "CRC Child-Resistant Cap Seal": it can process 11,526 vials per day against a demand of 16,000 vials, so it falls short of demand by 28.0%. Once downtime and scrap are counted, its cycle time grows from 3.6 s to 4.5 s, against a takt of 3.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.