Randomized Double-Blind Clinical Trial Kit Pack
Product family: Phase-III Placebo-Controlled Kits.
Flow: CRO Trial Sponsors → Randomization Label Print → Double-Blind Bottle Over-Encap → Tamper Wallet Blister Pack → Barcode Blind Check 100% → GDP Phase-III Depot Dispatch → Global Clinical Trial Sites
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Randomization Label Print | 22.9 s | 45 min | 94% | 99.1% | 1,275 | 1,360 (1.60 d) | 1,025 |
| 2. Double-Blind Bottle Over-Encap | 26.7 s | 75 min | 89% | 97.6% | 1,275 | 1,530 (1.80 d) | 781 |
| 3. Tamper Wallet Blister Pack | 34.0 s | 65 min | 84% | 96.1% | 1,275 | 1,785 (2.10 d) | 579 |
| 4. Barcode Blind Check 100% | 24.8 s | 35 min | 91% | 98.2% | 680 | 1,020 (1.20 d) | 878 |
| 5. GDP Phase-III Depot Dispatch | 19.7 s | 15 min | 95% | 99.4% | 425 | 1,190 (1.40 d) | 1,208 |
Key figures
- Takt time
- 31.8 s
- Lead time
- 9.90 d
- Value-added time
- 128 s
- Process cycle efficiency (PCE)
- 0.048%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 850 packs
- Line capacity per day
- 579 packs
- Bottleneck
- Tamper Wallet Blister Pack
Reading the bottleneck
The bottleneck is "Tamper Wallet Blister Pack": it can process 579 packs per day against a demand of 850 packs, so it falls short of demand by 31.8%. Once downtime and scrap are counted, its cycle time grows from 34.0 s to 42.1 s, against a takt of 31.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 6.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oral Solid Dose, Tablets & Blister: Oral Solid Dose, Tablets & Blister
- High-Shear Granulation & Film-Coated Tablet
- High-Speed ALU-ALU Tropicalized Blister Line
- Enteric Pellet Hard-Gelatin Capsule Filling
- RH<12% Low-Humidity Effervescent Tube Line
- Oral Suspension Syrup & Child-Safe Cap Line
- OEB-5 High-Potency Contained Oncology Tablet
- Rotary Die Liquid-Fill Softgel Vitamin Line
- 4-Lane Aluminum Foil Stick-Pack Powder Line
- Thin-Film Orally Disintegrating Strip Line
- Dual-Release Fixed-Dose Bilayer Tablet
- Continuous Melt-Pour Suppository PVC Shell