OEB-5 High-Potency Contained Oncology Tablet
Product family: Targeted Kinase Inhibitors.
Flow: HPAPI Suppliers → Isolator Containment Dispense → Contained Roller Compactor → Contained Rotary Tablet Press → Dedicated Wash-In-Place Coat → Bottle Induction & Trace Pack → Specialty Oncology Hospitals
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Isolator Containment Dispense | 2.8 s | 45 min | 94% | 99.1% | 21,000 | 22,400 (1.60 d) | 17,367 |
| 2. Contained Roller Compactor | 3.2 s | 75 min | 89% | 97.6% | 21,000 | 25,200 (1.80 d) | 13,844 |
| 3. Contained Rotary Tablet Press | 4.1 s | 65 min | 84% | 96.1% | 21,000 | 29,400 (2.10 d) | 10,120 |
| 4. Dedicated Wash-In-Place Coat | 3.0 s | 35 min | 91% | 98.2% | 11,200 | 16,800 (1.20 d) | 15,303 |
| 5. Bottle Induction & Trace Pack | 2.4 s | 15 min | 95% | 99.4% | 7,000 | 19,600 (1.40 d) | 20,539 |
Key figures
- Takt time
- 3.9 s
- Lead time
- 9.90 d
- Value-added time
- 15.5 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 14,000 units
- Line capacity per day
- 10,120 units
- Bottleneck
- Contained Rotary Tablet Press
Reading the bottleneck
The bottleneck is "Contained Rotary Tablet Press": it can process 10,120 units per day against a demand of 14,000 units, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 4.1 s to 5.1 s, against a takt of 3.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.8 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oral Solid Dose, Tablets & Blister: Oral Solid Dose, Tablets & Blister
- High-Shear Granulation & Film-Coated Tablet
- High-Speed ALU-ALU Tropicalized Blister Line
- Enteric Pellet Hard-Gelatin Capsule Filling
- RH<12% Low-Humidity Effervescent Tube Line
- Oral Suspension Syrup & Child-Safe Cap Line
- Rotary Die Liquid-Fill Softgel Vitamin Line
- 4-Lane Aluminum Foil Stick-Pack Powder Line
- Thin-Film Orally Disintegrating Strip Line
- Dual-Release Fixed-Dose Bilayer Tablet
- Randomized Double-Blind Clinical Trial Kit Pack
- Continuous Melt-Pour Suppository PVC Shell