High-Speed ALU-ALU Tropicalized Blister Line
Product family: Moisture-Sensitive Blister Packs.
Flow: Cold-Form Aluminum Foil Supplier → Cold-Form Aluminum Draw → Rotary Brush Tablet Feeding → Vision Missing/Broken Camera → Lidding Seal & Laser Lot Print → High-Speed Cartoner & Weigh → Export Tropical Markets
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Cold-Form Aluminum Draw | 1.2 s | 45 min | 94% | 99.1% | 54,000 | 57,600 (1.60 d) | 40,522 |
| 2. Rotary Brush Tablet Feeding | 1.3 s | 75 min | 89% | 97.6% | 54,000 | 64,800 (1.80 d) | 34,077 |
| 3. Vision Missing/Broken Camera | 1.6 s | 65 min | 84% | 96.1% | 54,000 | 75,600 (2.10 d) | 25,933 |
| 4. Lidding Seal & Laser Lot Print | 1.2 s | 35 min | 91% | 98.2% | 28,800 | 43,200 (1.20 d) | 38,258 |
| 5. High-Speed Cartoner & Weigh | 1.2 s | 15 min | 95% | 99.4% | 18,000 | 50,400 (1.40 d) | 41,077 |
Key figures
- Takt time
- 1.5 s
- Lead time
- 9.90 d
- Value-added time
- 6.5 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 36,000 packs
- Line capacity per day
- 25,933 packs
- Bottleneck
- Vision Missing/Broken Camera
Reading the bottleneck
The bottleneck is "Vision Missing/Broken Camera": it can process 25,933 packs per day against a demand of 36,000 packs, so it falls short of demand by 28.0%. Once downtime and scrap are counted, its cycle time grows from 1.6 s to 2.0 s, against a takt of 1.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oral Solid Dose, Tablets & Blister: Oral Solid Dose, Tablets & Blister
- High-Shear Granulation & Film-Coated Tablet
- Enteric Pellet Hard-Gelatin Capsule Filling
- RH<12% Low-Humidity Effervescent Tube Line
- Oral Suspension Syrup & Child-Safe Cap Line
- OEB-5 High-Potency Contained Oncology Tablet
- Rotary Die Liquid-Fill Softgel Vitamin Line
- 4-Lane Aluminum Foil Stick-Pack Powder Line
- Thin-Film Orally Disintegrating Strip Line
- Dual-Release Fixed-Dose Bilayer Tablet
- Randomized Double-Blind Clinical Trial Kit Pack
- Continuous Melt-Pour Suppository PVC Shell