RH<12% Low-Humidity Effervescent Tube Line
Product family: Vitamin & Analgesic Fizz Tabs.
Flow: Citric & Bicarbonate Suppliers → Dry Roller Compaction → Dehumidified Tablet Press → Stack-Count Tube Drop & Cap → Desiccant Plug Torque Check → Carton Tray & Shrink Bundle → OTC Pharmacy Chains
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Dry Roller Compaction | 1.2 s | 45 min | 94% | 99.1% | 180,000 | 192,000 (1.60 d) | 40,522 |
| 2. Dehumidified Tablet Press | 1.2 s | 75 min | 89% | 97.6% | 180,000 | 216,000 (1.80 d) | 36,917 |
| 3. Stack-Count Tube Drop & Cap | 1.2 s | 65 min | 84% | 96.1% | 180,000 | 252,000 (2.10 d) | 34,577 |
| 4. Desiccant Plug Torque Check | 1.2 s | 35 min | 91% | 98.2% | 96,000 | 144,000 (1.20 d) | 38,258 |
| 5. Carton Tray & Shrink Bundle | 1.2 s | 15 min | 95% | 99.4% | 60,000 | 168,000 (1.40 d) | 41,077 |
Key figures
- Takt time
- 0.5 s
- Lead time
- 9.90 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 120,000 units
- Line capacity per day
- 34,577 units
- Bottleneck
- Stack-Count Tube Drop & Cap
Reading the bottleneck
The bottleneck is "Stack-Count Tube Drop & Cap": it can process 34,577 units per day against a demand of 120,000 units, so it falls short of demand by 71.2%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oral Solid Dose, Tablets & Blister: Oral Solid Dose, Tablets & Blister
- High-Shear Granulation & Film-Coated Tablet
- High-Speed ALU-ALU Tropicalized Blister Line
- Enteric Pellet Hard-Gelatin Capsule Filling
- Oral Suspension Syrup & Child-Safe Cap Line
- OEB-5 High-Potency Contained Oncology Tablet
- Rotary Die Liquid-Fill Softgel Vitamin Line
- 4-Lane Aluminum Foil Stick-Pack Powder Line
- Thin-Film Orally Disintegrating Strip Line
- Dual-Release Fixed-Dose Bilayer Tablet
- Randomized Double-Blind Clinical Trial Kit Pack
- Continuous Melt-Pour Suppository PVC Shell