4-Lane Aluminum Foil Stick-Pack Powder Line
Product family: Oral Electrolytes & Probiotics.
Flow: Barrier Foil Supplier → V-Blender Homogeneous Mix → 4-Lane Servo Auger Stick Fill → Ultrasonic Tear-Notch Seal → Inline Weight & Leak Probe → Auto Stick Cartoner Box → OTC Consumer Health
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. V-Blender Homogeneous Mix | 1.2 s | 45 min | 94% | 99.1% | 142,500 | 152,000 (1.60 d) | 40,522 |
| 2. 4-Lane Servo Auger Stick Fill | 1.2 s | 75 min | 89% | 97.6% | 142,500 | 171,000 (1.80 d) | 36,917 |
| 3. Ultrasonic Tear-Notch Seal | 1.2 s | 65 min | 84% | 96.1% | 142,500 | 199,500 (2.10 d) | 34,577 |
| 4. Inline Weight & Leak Probe | 1.2 s | 35 min | 91% | 98.2% | 76,000 | 114,000 (1.20 d) | 38,258 |
| 5. Auto Stick Cartoner Box | 1.2 s | 15 min | 95% | 99.4% | 47,500 | 133,000 (1.40 d) | 41,077 |
Key figures
- Takt time
- 0.6 s
- Lead time
- 9.90 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 95,000 packs
- Line capacity per day
- 34,577 packs
- Bottleneck
- Ultrasonic Tear-Notch Seal
Reading the bottleneck
The bottleneck is "Ultrasonic Tear-Notch Seal": it can process 34,577 packs per day against a demand of 95,000 packs, so it falls short of demand by 63.6%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oral Solid Dose, Tablets & Blister: Oral Solid Dose, Tablets & Blister
- High-Shear Granulation & Film-Coated Tablet
- High-Speed ALU-ALU Tropicalized Blister Line
- Enteric Pellet Hard-Gelatin Capsule Filling
- RH<12% Low-Humidity Effervescent Tube Line
- Oral Suspension Syrup & Child-Safe Cap Line
- OEB-5 High-Potency Contained Oncology Tablet
- Rotary Die Liquid-Fill Softgel Vitamin Line
- Thin-Film Orally Disintegrating Strip Line
- Dual-Release Fixed-Dose Bilayer Tablet
- Randomized Double-Blind Clinical Trial Kit Pack
- Continuous Melt-Pour Suppository PVC Shell