2.8m Heavy Treated Timber Power Cable Drum

Product family: NEMA / DIN Returnable Reels.

Flow: HT Structural Softwood → Rotary Flange Jig & Saw Ring → CNC Arbor Bore & Tire Strip → Stave Lagging & Tie-Rod Torque → ISPM-15 Stamp & Bolt Check → Knocked-Down Flat Pack Ship → HV Subsea & XLPE Cable Mills

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 2.8m Heavy Treated Timber Power Cable DrumSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. HT Structural Softwood → Rotary Flange Jig & Saw Ring (324 s) → CNC Arbor Bore & Tire Strip (403 s) → Stave Lagging & Tie-Rod Torque (530 s) → ISPM-15 Stamp & Bolt Check (363 s) → Knocked-Down Flat Pack Ship (275 s) → HV Subsea & XLPE Cable Mills.SUPPLIERHT StructuralSoftwoodI1.80 d1Rotary Flange Jig& Saw RingC/T 324 sI1.60 d2CNC Arbor Bore &Tire StripC/T 403 sI2.80 d3Stave Lagging &Tie-Rod TorqueC/T 530 sI1.20 d4ISPM-15 Stamp &Bolt CheckC/T 363 sI1.00 d5Knocked-Down FlatPack ShipC/T 275 sI2.00 dCUSTOMERHV Subsea &XLPE Cable…110 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Rotary Flange Jig & Saw Ring324 s20 min94%98.4%165198 (1.80 d)152
2. CNC Arbor Bore & Tire Strip403 s25 min91%97.6%110176 (1.60 d)116
3. Stave Lagging & Tie-Rod Torque530 s45 min84%95.8%165308 (2.80 d)79
4. ISPM-15 Stamp & Bolt Check363 s20 min93%98.2%55132 (1.20 d)130
5. Knocked-Down Flat Pack Ship275 s8 min97%99.4%44110 (1.00 d)185

Key figures

Takt time
491 s
Lead time
10.4 d
Value-added time
1,895 s
Process cycle efficiency (PCE)
0.34%
Rolled throughput yield (RTY)
89.8%
Customer demand per day
110 units
Line capacity per day
79 units
Bottleneck
Stave Lagging & Tie-Rod Torque

Reading the bottleneck

The bottleneck is "Stave Lagging & Tie-Rod Torque": it can process 79 units per day against a demand of 110 units, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 530 s to 659 s, against a takt of 491 s. The largest loss at this step is equipment downtime (uptime 84%), about 101 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.