Micro-Agglomerated TCA-Free Wine Cork Stopper
Product family: Molded Individual Zero-TCA Corks.
Flow: Alentejo Cork Oak Bark → Boil, Grind & Size Separation → Supercritical CO2 TCA Extract → Individual Mold Cure Reaction → Centerless Sand & Food Silicone → Laser Brand & SO2 Clean Bag → Winery Bottling Lines
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Boil, Grind & Size Separation | 1.2 s | 20 min | 94% | 98.4% | 142,500 | 171,000 (1.80 d) | 41,007 |
| 2. Supercritical CO2 TCA Extract | 1.2 s | 25 min | 91% | 97.6% | 95,000 | 152,000 (1.60 d) | 38,857 |
| 3. Individual Mold Cure Reaction | 1.2 s | 45 min | 84% | 95.8% | 142,500 | 266,000 (2.80 d) | 35,005 |
| 4. Centerless Sand & Food Silicone | 1.2 s | 20 min | 93% | 98.2% | 47,500 | 114,000 (1.20 d) | 39,270 |
| 5. Laser Brand & SO2 Clean Bag | 1.2 s | 8 min | 97% | 99.4% | 38,000 | 95,000 (1.00 d) | 42,424 |
Key figures
- Takt time
- 0.6 s
- Lead time
- 10.4 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 89.8%
- Customer demand per day
- 95,000 units
- Line capacity per day
- 35,005 units
- Bottleneck
- Individual Mold Cure Reaction
Reading the bottleneck
The bottleneck is "Individual Mold Cure Reaction": it can process 35,005 units per day against a demand of 95,000 units, so it falls short of demand by 63.2%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Sawmills, Timber, CLT & Wood Panels: Sawmills, Timber, CLT & Wood Panels
- High-Speed Chipper-Canter Structural Sawmill
- Mass-Timber Cross-Laminated Timber (CLT) Press
- Continuous Medium Density Fiberboard
- OSB/3 Oriented Strand Structural Sheathing Line
- High-Speed Automated EUR EPAL Pallet Nailing
- 225L Bordeaux Toasted French Oak Wine Barrel
- Curved Glued-Laminated Roof Span Arch Beam
- 13-Ply Marine Film-Faced Concrete Form Plywood
- ENplus-A1 White Wood Biofuel Heating Pellets
- 2.8m Heavy Treated Timber Power Cable Drum
- Carbonized High-Density Thermo-Bamboo Decking