OSB/3 Oriented Strand Structural Sheathing Line

Product family: Moisture-Resistant Roof Panels.

Flow: Small-Diameter Pine Logs → Long-Knife Ring Flaker Stand → 3-Layer Drum Dryer & Blend → Cross-Oriented Face/Core Mat → Continuous Press Steam Injection → Tongue & Groove Edge Seal → Timber Frame & Packaging

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: OSB/3 Oriented Strand Structural Sheathing LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Small-Diameter Pine Logs → Long-Knife Ring Flaker Stand (86.0 s) → 3-Layer Drum Dryer & Blend (107 s) → Cross-Oriented Face/Core Mat (141 s) → Continuous Press Steam Injection (97.0 s) → Tongue & Groove Edge Seal (73.0 s) → Timber Frame & Packaging.SUPPLIERSmall-DiameterPine LogsI1.80 d1Long-Knife RingFlaker StandC/T 86.0 sI1.60 d23-Layer DrumDryer & BlendC/T 107 sI2.80 d3Cross-OrientedFace/Core MatC/T 141 sI1.20 d4Continuous PressSteam InjectionC/T 97.0 sI1.00 d5Tongue & GrooveEdge SealC/T 73.0 sI2.00 dCUSTOMERTimber Frame &Packaging620 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Long-Knife Ring Flaker Stand86.0 s20 min94%98.4%9301,116 (1.80 d)863
2. 3-Layer Drum Dryer & Blend107 s25 min91%97.6%620992 (1.60 d)660
3. Cross-Oriented Face/Core Mat141 s45 min84%95.8%9301,736 (2.80 d)452
4. Continuous Press Steam Injection97.0 s20 min93%98.2%310744 (1.20 d)740
5. Tongue & Groove Edge Seal73.0 s8 min97%99.4%248620 (1.00 d)1,054

Key figures

Takt time
131 s
Lead time
10.4 d
Value-added time
504 s
Process cycle efficiency (PCE)
0.060%
Rolled throughput yield (RTY)
89.8%
Customer demand per day
620 tonnes
Line capacity per day
452 tonnes
Bottleneck
Cross-Oriented Face/Core Mat

Reading the bottleneck

The bottleneck is "Cross-Oriented Face/Core Mat": it can process 452 tonnes per day against a demand of 620 tonnes, so it falls short of demand by 27.1%. Once downtime and scrap are counted, its cycle time grows from 141 s to 175 s, against a takt of 131 s. The largest loss at this step is equipment downtime (uptime 84%), about 26.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.