Carbonized High-Density Thermo-Bamboo Decking
Product family: 1860MPa Strand-Woven Planks.
Flow: Moso 5-Yr Harvested Bamboo → Split, Crush & Steam Carbonize → Kiln Dry & Dip Phenolic Glue → 2500T High-Density Hot Press → Diamond T&G Clip Groove Mill → UV Oil Coat & Strap Pallet → Landscape & Marina Builders
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Split, Crush & Steam Carbonize | 52.0 s | 20 min | 94% | 98.4% | 1,020 | 1,224 (1.80 d) | 946 |
| 2. Kiln Dry & Dip Phenolic Glue | 65.0 s | 25 min | 91% | 97.6% | 680 | 1,088 (1.60 d) | 717 |
| 3. 2500T High-Density Hot Press | 86.0 s | 45 min | 84% | 95.8% | 1,020 | 1,904 (2.80 d) | 488 |
| 4. Diamond T&G Clip Groove Mill | 59.0 s | 20 min | 93% | 98.2% | 340 | 816 (1.20 d) | 799 |
| 5. UV Oil Coat & Strap Pallet | 44.0 s | 8 min | 97% | 99.4% | 272 | 680 (1.00 d) | 1,157 |
Key figures
- Takt time
- 79.4 s
- Lead time
- 10.4 d
- Value-added time
- 306 s
- Process cycle efficiency (PCE)
- 0.054%
- Rolled throughput yield (RTY)
- 89.8%
- Customer demand per day
- 680 parts
- Line capacity per day
- 488 parts
- Bottleneck
- 2500T High-Density Hot Press
Reading the bottleneck
The bottleneck is "2500T High-Density Hot Press": it can process 488 parts per day against a demand of 680 parts, so it falls short of demand by 28.2%. Once downtime and scrap are counted, its cycle time grows from 86.0 s to 107 s, against a takt of 79.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 16.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Sawmills, Timber, CLT & Wood Panels: Sawmills, Timber, CLT & Wood Panels
- High-Speed Chipper-Canter Structural Sawmill
- Mass-Timber Cross-Laminated Timber (CLT) Press
- Continuous Medium Density Fiberboard
- OSB/3 Oriented Strand Structural Sheathing Line
- High-Speed Automated EUR EPAL Pallet Nailing
- 225L Bordeaux Toasted French Oak Wine Barrel
- Curved Glued-Laminated Roof Span Arch Beam
- 13-Ply Marine Film-Faced Concrete Form Plywood
- ENplus-A1 White Wood Biofuel Heating Pellets
- 2.8m Heavy Treated Timber Power Cable Drum
- Micro-Agglomerated TCA-Free Wine Cork Stopper