High-Speed Chipper-Canter Structural Sawmill

Product family: C24 Kiln-Dried Framing Studs.

Flow: Spruce & Pine Roundwood Logs → Laser Log Shape Rotation → Chipper-Canter Multi-Saw Line → Auto Sticker-Stacker Frame → Progressive Steam Kiln 12% → MSR Strength Planer & Wrap → Timber Merchants & Roofers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Speed Chipper-Canter Structural SawmillSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Spruce & Pine Roundwood Logs → Laser Log Shape Rotation (127 s) → Chipper-Canter Multi-Saw Line (158 s) → Auto Sticker-Stacker Frame (208 s) → Progressive Steam Kiln 12% (143 s) → MSR Strength Planer & Wrap (108 s) → Timber Merchants & Roofers.SUPPLIERSpruce & PineRoundwood LogsI1.80 d1Laser Log ShapeRotationC/T 127 sI1.60 d2Chipper-CanterMulti-Saw LineC/T 158 sI2.80 d3AutoSticker-Stacker…C/T 208 sI1.20 d4Progressive SteamKiln 12%C/T 143 sI1.00 d5MSR StrengthPlaner & WrapC/T 108 sI2.00 dCUSTOMERTimberMerchants &…420 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Laser Log Shape Rotation127 s20 min94%98.4%630756 (1.80 d)584
2. Chipper-Canter Multi-Saw Line158 s25 min91%97.6%420672 (1.60 d)447
3. Auto Sticker-Stacker Frame208 s45 min84%95.8%6301,176 (2.80 d)306
4. Progressive Steam Kiln 12%143 s20 min93%98.2%210504 (1.20 d)502
5. MSR Strength Planer & Wrap108 s8 min97%99.4%168420 (1.00 d)712

Key figures

Takt time
193 s
Lead time
10.4 d
Value-added time
744 s
Process cycle efficiency (PCE)
0.088%
Rolled throughput yield (RTY)
89.8%
Customer demand per day
420 tonnes
Line capacity per day
306 tonnes
Bottleneck
Auto Sticker-Stacker Frame

Reading the bottleneck

The bottleneck is "Auto Sticker-Stacker Frame": it can process 306 tonnes per day against a demand of 420 tonnes, so it falls short of demand by 27.0%. Once downtime and scrap are counted, its cycle time grows from 208 s to 258 s, against a takt of 193 s. The largest loss at this step is equipment downtime (uptime 84%), about 39.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.