Mass-Timber Cross-Laminated Timber (CLT) Press
Product family: 16m Structural Floor Slabs.
Flow: C24 Spruce Finger-Jointed → Moisture & E-Modulus Machine → Twin-Face Finger Joint Cure → Cross-Lay PUR Glue Vacuum Press → 5-Axis Giant Portal Window Cut → Crane Lifting Eye & Moisture Tarps → Mass-Timber Multi-Story
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Moisture & E-Modulus Machine | 1,273 s | 20 min | 94% | 98.4% | 42 | 50 (1.79 d) | 39 |
| 2. Twin-Face Finger Joint Cure | 1,581 s | 25 min | 91% | 97.6% | 28 | 45 (1.61 d) | 29 |
| 3. Cross-Lay PUR Glue Vacuum Press | 2,083 s | 45 min | 84% | 95.8% | 42 | 78 (2.79 d) | 20 |
| 4. 5-Axis Giant Portal Window Cut | 1,427 s | 20 min | 93% | 98.2% | 14 | 34 (1.21 d) | 33 |
| 5. Crane Lifting Eye & Moisture Tarps | 1,080 s | 8 min | 97% | 99.4% | 11 | 28 (1.00 d) | 47 |
Key figures
- Takt time
- 1,929 s
- Lead time
- 10.5 d
- Value-added time
- 7,444 s
- Process cycle efficiency (PCE)
- 1.3%
- Rolled throughput yield (RTY)
- 89.8%
- Customer demand per day
- 28 parts
- Line capacity per day
- 20 parts
- Bottleneck
- Cross-Lay PUR Glue Vacuum Press
Reading the bottleneck
The bottleneck is "Cross-Lay PUR Glue Vacuum Press": it can process 20 parts per day against a demand of 28 parts, so it falls short of demand by 28.0%. Once downtime and scrap are counted, its cycle time grows from 2,083 s to 2,588 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 84%), about 397 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Sawmills, Timber, CLT & Wood Panels: Sawmills, Timber, CLT & Wood Panels
- High-Speed Chipper-Canter Structural Sawmill
- Continuous Medium Density Fiberboard
- OSB/3 Oriented Strand Structural Sheathing Line
- High-Speed Automated EUR EPAL Pallet Nailing
- 225L Bordeaux Toasted French Oak Wine Barrel
- Curved Glued-Laminated Roof Span Arch Beam
- 13-Ply Marine Film-Faced Concrete Form Plywood
- ENplus-A1 White Wood Biofuel Heating Pellets
- 2.8m Heavy Treated Timber Power Cable Drum
- Micro-Agglomerated TCA-Free Wine Cork Stopper
- Carbonized High-Density Thermo-Bamboo Decking