Continuous Medium Density Fiberboard

Product family: 18mm E0 Furniture Grade MDF.

Flow: Forestry Thinnings & Chips → Pressurized Steam Defibrator → MDI Resin Blowline & Flash Dry → Forming Station Scalping Roll → 60m Continuous Steel-Belt Press → Star Cooler, Sand & Cut Pack → Laminate & Furniture Mills

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Continuous Medium Density FiberboardSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Forestry Thinnings & Chips → Pressurized Steam Defibrator (97.0 s) → MDI Resin Blowline & Flash Dry (121 s) → Forming Station Scalping Roll (159 s) → 60m Continuous Steel-Belt Press (109 s) → Star Cooler, Sand & Cut Pack (82.0 s) → Laminate & Furniture Mills.SUPPLIERForestryThinnings &ChipsI1.80 d1Pressurized SteamDefibratorC/T 97.0 sI1.60 d2MDI ResinBlowline & Flash…C/T 121 sI2.80 d3Forming StationScalping RollC/T 159 sI1.20 d460m ContinuousSteel-Belt PressC/T 109 sI1.00 d5Star Cooler, Sand& Cut PackC/T 82.0 sI2.00 dCUSTOMERLaminate &Furniture Mills550 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Pressurized Steam Defibrator97.0 s20 min94%98.4%825990 (1.80 d)765
2. MDI Resin Blowline & Flash Dry121 s25 min91%97.6%550880 (1.60 d)584
3. Forming Station Scalping Roll159 s45 min84%95.8%8251,540 (2.80 d)401
4. 60m Continuous Steel-Belt Press109 s20 min93%98.2%275660 (1.20 d)659
5. Star Cooler, Sand & Cut Pack82.0 s8 min97%99.4%220550 (1.00 d)938

Key figures

Takt time
147 s
Lead time
10.4 d
Value-added time
568 s
Process cycle efficiency (PCE)
0.067%
Rolled throughput yield (RTY)
89.8%
Customer demand per day
550 tonnes
Line capacity per day
401 tonnes
Bottleneck
Forming Station Scalping Roll

Reading the bottleneck

The bottleneck is "Forming Station Scalping Roll": it can process 401 tonnes per day against a demand of 550 tonnes, so it falls short of demand by 27.1%. Once downtime and scrap are counted, its cycle time grows from 159 s to 198 s, against a takt of 147 s. The largest loss at this step is equipment downtime (uptime 84%), about 30.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.