15-Inch Synthetic Vision Cockpit LCD/OLED

Product family: NVG-Compatible Primary Displays.

Flow: Anti-reflective glass supplier → Index-Matched Optical Bond → Night-Vision NVIS Filter Seal → Dual Backlight Driver Mate → Rapid Decompression Bench → Luminance Uniformity & CIE → Airframer Flight Deck

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 15-Inch Synthetic Vision Cockpit LCD/OLEDSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Anti-reflective glass supplier → Index-Matched Optical Bond (353 s) → Night-Vision NVIS Filter Seal (403 s) → Dual Backlight Driver Mate (530 s) → Rapid Decompression Bench (344 s) → Luminance Uniformity & CIE (314 s) → Airframer Flight Deck.SUPPLIERAnti-reflectiveglass supplierI1.51 d1Index-MatchedOptical BondC/T 353 sI1.60 d2Night-Vision NVISFilter SealC/T 403 sI2.40 d3Dual BacklightDriver MateC/T 530 sI1.11 d4RapidDecompression…C/T 344 sI0.91 d5LuminanceUniformity & CIEC/T 314 sI1.51 dCUSTOMERAirframerFlight Deck55 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Index-Matched Optical Bond353 s35 min94%98.2%4483 (1.51 d)64
2. Night-Vision NVIS Filter Seal403 s15 min92%96.8%2888 (1.60 d)56
3. Dual Backlight Driver Mate530 s45 min85%93.8%55132 (2.40 d)37
4. Rapid Decompression Bench344 s20 min95%98.5%2261 (1.11 d)65
5. Luminance Uniformity & CIE314 s12 min96%99.1%1450 (0.91 d)73

Key figures

Takt time
491 s
Lead time
9.11 d
Value-added time
1,944 s
Process cycle efficiency (PCE)
0.79%
Rolled throughput yield (RTY)
87.0%
Customer demand per day
55 units
Line capacity per day
37 units
Bottleneck
Dual Backlight Driver Mate

Reading the bottleneck

The bottleneck is "Dual Backlight Driver Mate": it can process 37 units per day against a demand of 55 units, so it falls short of demand by 33.5%. Once downtime and scrap are counted, its cycle time grows from 530 s to 665 s, against a takt of 491 s. The largest loss at this step is equipment downtime (uptime 85%), about 93.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Avionics, Space & Flight Electronics: Avionics, Space & Flight Electronics