Encrypted Beyond-Line-of-Sight UAV Modem

Product family: Tactical Mesh Radio Links.

Flow: High-end FPGA supplier → 14-Layer Blind Via SMT → CNC Milled RF Shielding Lid → AES Crypto Key Provision → Thermal Cycling -40/+85°C → Over-The-Air Link Margin ATE → Tactical Drone OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Encrypted Beyond-Line-of-Sight UAV ModemSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. High-end FPGA supplier → 14-Layer Blind Via SMT (324 s) → CNC Milled RF Shielding Lid (369 s) → AES Crypto Key Provision (486 s) → Thermal Cycling -40/+85°C (315 s) → Over-The-Air Link Margin ATE (288 s) → Tactical Drone OEMs.SUPPLIERHigh-end FPGAsupplierI1.50 d114-Layer BlindVia SMTC/T 324 sI1.60 d2CNC Milled RFShielding LidC/T 369 sI2.40 d3AES Crypto KeyProvisionC/T 486 sI1.10 d4Thermal Cycling-40/+85°CC/T 315 sI0.90 d5Over-The-Air LinkMargin ATEC/T 288 sI1.50 dCUSTOMERTactical DroneOEMs60 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 14-Layer Blind Via SMT324 s35 min94%98.2%4890 (1.50 d)69
2. CNC Milled RF Shielding Lid369 s15 min92%96.8%3096 (1.60 d)61
3. AES Crypto Key Provision486 s45 min85%93.8%60144 (2.40 d)40
4. Thermal Cycling -40/+85°C315 s20 min95%98.5%2466 (1.10 d)71
5. Over-The-Air Link Margin ATE288 s12 min96%99.1%1554 (0.90 d)80

Key figures

Takt time
450 s
Lead time
9.07 d
Value-added time
1,782 s
Process cycle efficiency (PCE)
0.73%
Rolled throughput yield (RTY)
87.0%
Customer demand per day
60 units
Line capacity per day
40 units
Bottleneck
AES Crypto Key Provision

Reading the bottleneck

The bottleneck is "AES Crypto Key Provision": it can process 40 units per day against a demand of 60 units, so it falls short of demand by 33.6%. Once downtime and scrap are counted, its cycle time grows from 486 s to 610 s, against a takt of 450 s. The largest loss at this step is equipment downtime (uptime 85%), about 85.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Avionics, Space & Flight Electronics: Avionics, Space & Flight Electronics