AESA Airborne Phased-Array Radar Antenna

Product family: GaN Transmit/Receive Tiles.

Flow: GaN RF-device supplier → Die Attach AuSn Eutectic → Ribbon Bond Cleanroom Cell → Liquid Cold-Plate Integration → Hermetic Seam-Seal Test → Near-Field Anechoic Scan → Fighter & Patrol Aircraft

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: AESA Airborne Phased-Array Radar AntennaSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. GaN RF-device supplier → Die Attach AuSn Eutectic (1,944 s) → Ribbon Bond Cleanroom Cell (2,214 s) → Liquid Cold-Plate Integration (2,916 s) → Hermetic Seam-Seal Test (1,890 s) → Near-Field Anechoic Scan (1,728 s) → Fighter & Patrol Aircraft.SUPPLIERGaN RF-devicesupplierI1.50 d1Die Attach AuSnEutecticC/T 1,944 sI1.60 d2Ribbon BondCleanroom CellC/T 2,214 sI2.40 d3Liquid Cold-PlateIntegrationC/T 2,916 sI1.10 d4HermeticSeam-Seal TestC/T 1,890 sI0.90 d5Near-FieldAnechoic ScanC/T 1,728 sI1.50 dCUSTOMERFighter &Patrol Aircraft10 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Die Attach AuSn Eutectic1,944 s35 min94%98.2%815 (1.50 d)12
2. Ribbon Bond Cleanroom Cell2,214 s15 min92%96.8%516 (1.60 d)10
3. Liquid Cold-Plate Integration2,916 s45 min85%93.8%1024 (2.40 d)7
4. Hermetic Seam-Seal Test1,890 s20 min95%98.5%411 (1.10 d)12
5. Near-Field Anechoic Scan1,728 s12 min96%99.1%39 (0.90 d)14

Key figures

Takt time
2,700 s
Lead time
9.40 d
Value-added time
10,692 s
Process cycle efficiency (PCE)
4.2%
Rolled throughput yield (RTY)
87.0%
Customer demand per day
10 units
Line capacity per day
7 units
Bottleneck
Liquid Cold-Plate Integration

Reading the bottleneck

The bottleneck is "Liquid Cold-Plate Integration": it can process 7 units per day against a demand of 10 units, so it falls short of demand by 33.6%. Once downtime and scrap are counted, its cycle time grows from 2,916 s to 3,657 s, against a takt of 2,700 s. The largest loss at this step is equipment downtime (uptime 85%), about 515 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.