Triple-Redundant Flight Control Computer

Product family: DO-254 Primary FCC Box.

Flow: Rad-hard semiconductor supplier → Class-3 Fine-Pitch SMT → Automated Optical & X-Ray → Parylene Conformal Vapor Coat → Chassis Card-Edge Backplane → Hardware-in-Loop Flight Sim → OEM Cockpit Avionics Bay

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Triple-Redundant Flight Control ComputerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Rad-hard semiconductor supplier → Class-3 Fine-Pitch SMT (810 s) → Automated Optical & X-Ray (923 s) → Parylene Conformal Vapor Coat (1,215 s) → Chassis Card-Edge Backplane (788 s) → Hardware-in-Loop Flight Sim (720 s) → OEM Cockpit Avionics Bay.SUPPLIERRad-hardsemiconductorsupplierI1.50 d1Class-3Fine-Pitch SMTC/T 810 sI1.58 d2Automated Optical& X-RayC/T 923 sI2.42 d3ParyleneConformal Vapor…C/T 1,215 sI1.08 d4Chassis Card-EdgeBackplaneC/T 788 sI0.92 d5Hardware-in-LoopFlight SimC/T 720 sI1.50 dCUSTOMEROEM CockpitAvionics Bay24 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Class-3 Fine-Pitch SMT810 s35 min94%98.2%1936 (1.50 d)28
2. Automated Optical & X-Ray923 s15 min92%96.8%1238 (1.58 d)24
3. Parylene Conformal Vapor Coat1,215 s45 min85%93.8%2458 (2.42 d)16
4. Chassis Card-Edge Backplane788 s20 min95%98.5%1026 (1.08 d)29
5. Hardware-in-Loop Flight Sim720 s12 min96%99.1%622 (0.92 d)32

Key figures

Takt time
1,125 s
Lead time
9.17 d
Value-added time
4,456 s
Process cycle efficiency (PCE)
1.8%
Rolled throughput yield (RTY)
87.0%
Customer demand per day
24 units
Line capacity per day
16 units
Bottleneck
Parylene Conformal Vapor Coat

Reading the bottleneck

The bottleneck is "Parylene Conformal Vapor Coat": it can process 16 units per day against a demand of 24 units, so it falls short of demand by 33.6%. Once downtime and scrap are counted, its cycle time grows from 1,215 s to 1,524 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 85%), about 214 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.