5G-Immune Radar Altimeter LRUs
Product family: Precision Flare Height Radars.
Flow: RF component supplier → Machined RF Cavity Filter → SMT RF Microstrip Assembly → Gasketed EMI Lid Screw → Delay-Line Altitude Loop Sim → Altitude ±1ft Linearity QC → Belly Avionics Bay
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Machined RF Cavity Filter | 405 s | 35 min | 94% | 98.2% | 38 | 72 (1.50 d) | 55 |
| 2. SMT RF Microstrip Assembly | 461 s | 15 min | 92% | 96.8% | 24 | 77 (1.60 d) | 49 |
| 3. Gasketed EMI Lid Screw | 608 s | 45 min | 85% | 93.8% | 48 | 115 (2.40 d) | 32 |
| 4. Delay-Line Altitude Loop Sim | 394 s | 20 min | 95% | 98.5% | 19 | 53 (1.10 d) | 57 |
| 5. Altitude ±1ft Linearity QC | 360 s | 12 min | 96% | 99.1% | 12 | 43 (0.90 d) | 64 |
Key figures
- Takt time
- 563 s
- Lead time
- 9.08 d
- Value-added time
- 2,228 s
- Process cycle efficiency (PCE)
- 0.91%
- Rolled throughput yield (RTY)
- 87.0%
- Customer demand per day
- 48 units
- Line capacity per day
- 32 units
- Bottleneck
- Gasketed EMI Lid Screw
Reading the bottleneck
The bottleneck is "Gasketed EMI Lid Screw": it can process 32 units per day against a demand of 48 units, so it falls short of demand by 33.6%. Once downtime and scrap are counted, its cycle time grows from 608 s to 763 s, against a takt of 563 s. The largest loss at this step is equipment downtime (uptime 85%), about 107 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Avionics, Space & Flight Electronics: Avionics, Space & Flight Electronics
- Triple-Redundant Flight Control Computer
- Ring-Laser Gyroscope Inertial Reference IRU
- AESA Airborne Phased-Array Radar Antenna
- 15-Inch Synthetic Vision Cockpit LCD/OLED
- Dual-Channel FADEC Engine Control ECU
- Full-Fuselage PTFE Aerospace Cable Harness
- Ka-Band LEO Satellite Payload Transponder
- Crash-Survivable Flight Data & CVR Recorder
- Smart Heated Pitot-Static Air Data Probe
- Bipolar Full-Spectrum Mood Cabin Lighting
- Encrypted Beyond-Line-of-Sight UAV Modem