Bipolar Full-Spectrum Mood Cabin Lighting

Product family: CAN-Bus Aircraft Light Strips.

Flow: Automotive LED supplier → Metal-Core PCB SMT & Reflow → Silicone Extruded Lens Fit → DALI / ARINC Address Flash → Flammability FAR 25.853 Test → 24h Luminance Burn-In → Cabin Completion Shop

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Bipolar Full-Spectrum Mood Cabin LightingSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Automotive LED supplier → Metal-Core PCB SMT & Reflow (93.0 s) → Silicone Extruded Lens Fit (105 s) → DALI / ARINC Address Flash (139 s) → Flammability FAR 25.853 Test (90.0 s) → 24h Luminance Burn-In (82.0 s) → Cabin Completion Shop.SUPPLIERAutomotive LEDsupplierI1.50 d1Metal-Core PCBSMT & ReflowC/T 93.0 sI1.60 d2Silicone ExtrudedLens FitC/T 105 sI2.40 d3DALI / ARINCAddress FlashC/T 139 sI1.10 d4Flammability FAR25.853 TestC/T 90.0 sI0.90 d524h LuminanceBurn-InC/T 82.0 sI1.50 dCUSTOMERCabinCompletion Shop420 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Metal-Core PCB SMT & Reflow93.0 s35 min94%98.2%336630 (1.50 d)510
2. Silicone Extruded Lens Fit105 s15 min92%96.8%210672 (1.60 d)443
3. DALI / ARINC Address Flash139 s45 min85%93.8%4201,008 (2.40 d)294
4. Flammability FAR 25.853 Test90.0 s20 min95%98.5%168462 (1.10 d)530
5. 24h Luminance Burn-In82.0 s12 min96%99.1%105378 (0.90 d)593

Key figures

Takt time
129 s
Lead time
9.01 d
Value-added time
509 s
Process cycle efficiency (PCE)
0.10%
Rolled throughput yield (RTY)
87.0%
Customer demand per day
420 units
Line capacity per day
294 units
Bottleneck
DALI / ARINC Address Flash

Reading the bottleneck

The bottleneck is "DALI / ARINC Address Flash": it can process 294 units per day against a demand of 420 units, so it falls short of demand by 29.9%. Once downtime and scrap are counted, its cycle time grows from 139 s to 174 s, against a takt of 129 s. The largest loss at this step is equipment downtime (uptime 85%), about 24.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Avionics, Space & Flight Electronics: Avionics, Space & Flight Electronics