Fire-Retardant Phenolic Overhead Stowage Bin

Product family: Pivot-Down Aircraft Cabin Bins.

Flow: Phenolic fiber supplier → Pre-Form Crushed Core Press → Vacuum Mold & Release → Edge Seal & Latch Insert → OSU Flame/Smoke Sample Lot → Hinge Slam Endurance Audit → Cabin Interior Completion

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Fire-Retardant Phenolic Overhead Stowage BinSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Phenolic fiber supplier → Pre-Form Crushed Core Press (413 s) → Vacuum Mold & Release (534 s) → Edge Seal & Latch Insert (686 s) → OSU Flame/Smoke Sample Lot (470 s) → Hinge Slam Endurance Audit (432 s) → Cabin Interior Completion.SUPPLIERPhenolic fibersupplierI1.60 d1Pre-Form CrushedCore PressC/T 413 sI2.00 d2Vacuum Mold &ReleaseC/T 534 sI2.60 d3Edge Seal & LatchInsertC/T 686 sI1.31 d4OSU Flame/SmokeSample LotC/T 470 sI1.11 d5Hinge SlamEndurance AuditC/T 432 sI1.51 dCUSTOMERCabin InteriorCompletion85 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Pre-Form Crushed Core Press413 s20 min95%99.0%85136 (1.60 d)120
2. Vacuum Mold & Release534 s45 min90%97.2%68170 (2.00 d)83
3. Edge Seal & Latch Insert686 s60 min84%94.8%128221 (2.60 d)60
4. OSU Flame/Smoke Sample Lot470 s25 min93%97.8%43111 (1.31 d)99
5. Hinge Slam Endurance Audit432 s15 min95%96.8%4394 (1.11 d)111

Key figures

Takt time
635 s
Lead time
10.2 d
Value-added time
2,535 s
Process cycle efficiency (PCE)
0.46%
Rolled throughput yield (RTY)
86.4%
Customer demand per day
85 units
Line capacity per day
60 units
Bottleneck
Edge Seal & Latch Insert

Reading the bottleneck

The bottleneck is "Edge Seal & Latch Insert": it can process 60 units per day against a demand of 85 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 686 s to 861 s, against a takt of 635 s. The largest loss at this step is equipment downtime (uptime 84%), about 131 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.