Lightweight Aerospace ULD Composite Container

Product family: Aramid-Polycarbonate AKE Containers.

Flow: Aramid & polycarbonate supplier → Al Base Extrusion Frame → Thermoformed Polycarbonate Shell → Aramid Curtain & Zipper Sew → Huck-Bolt Corner Gusset → TSO-C90d Drop Load QC → Airline Cargo Fleets

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Lightweight Aerospace ULD Composite ContainerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aramid & polycarbonate supplier → Al Base Extrusion Frame (501 s) → Thermoformed Polycarbonate Shell (648 s) → Aramid Curtain & Zipper Sew (833 s) → Huck-Bolt Corner Gusset (571 s) → TSO-C90d Drop Load QC (525 s) → Airline Cargo Fleets.SUPPLIERAramid &polycarbonatesupplierI1.60 d1Al Base ExtrusionFrameC/T 501 sI2.00 d2ThermoformedPolycarbonate…C/T 648 sI2.60 d3Aramid Curtain &Zipper SewC/T 833 sI1.30 d4Huck-Bolt CornerGussetC/T 571 sI1.10 d5TSO-C90d DropLoad QCC/T 525 sI1.50 dCUSTOMERAirline CargoFleets70 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Al Base Extrusion Frame501 s20 min95%99.0%70112 (1.60 d)99
2. Thermoformed Polycarbonate Shell648 s45 min90%97.2%56140 (2.00 d)68
3. Aramid Curtain & Zipper Sew833 s60 min84%94.8%105182 (2.60 d)49
4. Huck-Bolt Corner Gusset571 s25 min93%97.8%3591 (1.30 d)81
5. TSO-C90d Drop Load QC525 s15 min95%96.8%3577 (1.10 d)91

Key figures

Takt time
771 s
Lead time
10.2 d
Value-added time
3,078 s
Process cycle efficiency (PCE)
0.56%
Rolled throughput yield (RTY)
86.4%
Customer demand per day
70 units
Line capacity per day
49 units
Bottleneck
Aramid Curtain & Zipper Sew

Reading the bottleneck

The bottleneck is "Aramid Curtain & Zipper Sew": it can process 49 units per day against a demand of 70 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 833 s to 1,046 s, against a takt of 771 s. The largest loss at this step is equipment downtime (uptime 84%), about 159 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.