3D Woven Carbon Jet Engine Fan Case

Product family: Lightweight Containment Cases.

Flow: Engineered composites house → 3D Jacquard Loom Weave → RTM Vacuum Resin Infusion → Oven Post-Cure Release → Abradable Acoustic Liner Mill → CMM Flange Bolt Circle QC → Nacelle & Engine Integration

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 3D Woven Carbon Jet Engine Fan CaseSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Engineered composites house → 3D Jacquard Loom Weave (2,194 s) → RTM Vacuum Resin Infusion (2,835 s) → Oven Post-Cure Release (3,645 s) → Abradable Acoustic Liner Mill (2,498 s) → CMM Flange Bolt Circle QC (2,295 s) → Nacelle & Engine Integration.SUPPLIEREngineeredcompositeshouseI1.63 d13D Jacquard LoomWeaveC/T 2,194 sI2.00 d2RTM Vacuum ResinInfusionC/T 2,835 sI2.63 d3Oven Post-CureReleaseC/T 3,645 sI1.31 d4AbradableAcoustic Liner…C/T 2,498 sI1.13 d5CMM Flange BoltCircle QCC/T 2,295 sI1.50 dCUSTOMERNacelle &Engine…16 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 3D Jacquard Loom Weave2,194 s20 min95%99.0%1626 (1.63 d)23
2. RTM Vacuum Resin Infusion2,835 s45 min90%97.2%1332 (2.00 d)16
3. Oven Post-Cure Release3,645 s60 min84%94.8%2442 (2.63 d)11
4. Abradable Acoustic Liner Mill2,498 s25 min93%97.8%821 (1.31 d)19
5. CMM Flange Bolt Circle QC2,295 s15 min95%96.8%818 (1.13 d)21

Key figures

Takt time
3,375 s
Lead time
10.4 d
Value-added time
13,467 s
Process cycle efficiency (PCE)
2.4%
Rolled throughput yield (RTY)
86.4%
Customer demand per day
16 units
Line capacity per day
11 units
Bottleneck
Oven Post-Cure Release

Reading the bottleneck

The bottleneck is "Oven Post-Cure Release": it can process 11 units per day against a demand of 16 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 3,645 s to 4,577 s, against a takt of 3,375 s. The largest loss at this step is equipment downtime (uptime 84%), about 694 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Carbon Composites & Autoclave: Carbon Composites & Autoclave