SiC-SiC Ceramic Matrix Exhaust Mixer
Product family: 1200°C Jet Nozzle Flaps.
Flow: Silicon carbide fiber supplier → 3D Ceramic Braiding → Slurry PIP & CVI Infiltrate → 1600°C Inert Furnace Cure → Diamond Ultrasonic CNC → Thermography Void Inspect → Next-Gen Turbofan Line
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 3D Ceramic Braiding | 702 s | 20 min | 95% | 99.0% | 25 | 40 (1.60 d) | 35 |
| 2. Slurry PIP & CVI Infiltrate | 907 s | 45 min | 90% | 97.2% | 20 | 50 (2.00 d) | 23 |
| 3. 1600°C Inert Furnace Cure | 1,166 s | 60 min | 84% | 94.8% | 38 | 65 (2.60 d) | 17 |
| 4. Diamond Ultrasonic CNC | 799 s | 25 min | 93% | 97.8% | 13 | 33 (1.32 d) | 27 |
| 5. Thermography Void Inspect | 734 s | 15 min | 95% | 96.8% | 13 | 28 (1.12 d) | 32 |
Key figures
- Takt time
- 1,080 s
- Lead time
- 10.3 d
- Value-added time
- 4,308 s
- Process cycle efficiency (PCE)
- 1.5%
- Rolled throughput yield (RTY)
- 86.4%
- Customer demand per day
- 25 parts
- Line capacity per day
- 17 parts
- Bottleneck
- 1600°C Inert Furnace Cure
Reading the bottleneck
The bottleneck is "1600°C Inert Furnace Cure": it can process 17 parts per day against a demand of 25 parts, so it falls short of demand by 32.7%. Once downtime and scrap are counted, its cycle time grows from 1,166 s to 1,464 s, against a takt of 1,080 s. The largest loss at this step is equipment downtime (uptime 84%), about 222 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Carbon Composites & Autoclave: Carbon Composites & Autoclave
- One-Piece CFRP Aircraft Fuselage Section
- Composite Upper/Lower Wing Skin Panel
- 3D Woven Carbon Jet Engine Fan Case
- Quartz-Honeycomb Nose Weather Radome
- Acoustic Carbon Cascade Thrust Reverser
- Composite Glass/Carbon Helicopter Rotor Blade
- Blended Aerodynamic Split-Scimitar Winglet
- CFRP Aluminum-Honeycomb Satellite Solar Bus
- Carbon Monocoque MALE UAV Airframe
- Fire-Retardant Phenolic Overhead Stowage Bin
- Lightweight Aerospace ULD Composite Container