Quartz-Honeycomb Nose Weather Radome
Product family: RF-Transparent Nose Cones.
Flow: Quartz fabric supplier → Quartz Bias Ply Layup → Aramid Core Splicing → Autoclave Co-Cure Bond → Lightning Diverter Strip Fit → ANECHOIC RF Transmissivity → Aircraft Forward Fuselage
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Quartz Bias Ply Layup | 878 s | 20 min | 95% | 99.0% | 20 | 32 (1.60 d) | 28 |
| 2. Aramid Core Splicing | 1,134 s | 45 min | 90% | 97.2% | 16 | 40 (2.00 d) | 18 |
| 3. Autoclave Co-Cure Bond | 1,458 s | 60 min | 84% | 94.8% | 30 | 52 (2.60 d) | 13 |
| 4. Lightning Diverter Strip Fit | 999 s | 25 min | 93% | 97.8% | 10 | 26 (1.30 d) | 22 |
| 5. ANECHOIC RF Transmissivity | 918 s | 15 min | 95% | 96.8% | 10 | 22 (1.10 d) | 25 |
Key figures
- Takt time
- 1,350 s
- Lead time
- 10.3 d
- Value-added time
- 5,387 s
- Process cycle efficiency (PCE)
- 1.9%
- Rolled throughput yield (RTY)
- 86.4%
- Customer demand per day
- 20 units
- Line capacity per day
- 13 units
- Bottleneck
- Autoclave Co-Cure Bond
Reading the bottleneck
The bottleneck is "Autoclave Co-Cure Bond": it can process 13 units per day against a demand of 20 units, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 1,458 s to 1,831 s, against a takt of 1,350 s. The largest loss at this step is equipment downtime (uptime 84%), about 278 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Carbon Composites & Autoclave: Carbon Composites & Autoclave
- One-Piece CFRP Aircraft Fuselage Section
- Composite Upper/Lower Wing Skin Panel
- 3D Woven Carbon Jet Engine Fan Case
- Acoustic Carbon Cascade Thrust Reverser
- Composite Glass/Carbon Helicopter Rotor Blade
- Blended Aerodynamic Split-Scimitar Winglet
- CFRP Aluminum-Honeycomb Satellite Solar Bus
- Carbon Monocoque MALE UAV Airframe
- Fire-Retardant Phenolic Overhead Stowage Bin
- SiC-SiC Ceramic Matrix Exhaust Mixer
- Lightweight Aerospace ULD Composite Container