CFRP Aluminum-Honeycomb Satellite Solar Bus

Product family: Zero-CTE Spacecraft Panels.

Flow: Pitch-carbon fiber supplier → Cleanroom Face-Sheet Cure → Perforated Al Core Prep → Autoclave Structural Bond → Ti Potting Insert CNC → Outgassing & Flatness Test → Cleanroom Spacecraft Bus

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: CFRP Aluminum-Honeycomb Satellite Solar BusSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Pitch-carbon fiber supplier → Cleanroom Face-Sheet Cure (1,755 s) → Perforated Al Core Prep (2,268 s) → Autoclave Structural Bond (2,916 s) → Ti Potting Insert CNC (1,998 s) → Outgassing & Flatness Test (1,836 s) → Cleanroom Spacecraft Bus.SUPPLIERPitch-carbonfiber supplierI1.60 d1CleanroomFace-Sheet CureC/T 1,755 sI2.00 d2Perforated AlCore PrepC/T 2,268 sI2.60 d3AutoclaveStructural BondC/T 2,916 sI1.30 d4Ti Potting InsertCNCC/T 1,998 sI1.10 d5Outgassing &Flatness TestC/T 1,836 sI1.50 dCUSTOMERCleanroomSpacecraft Bus10 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Cleanroom Face-Sheet Cure1,755 s20 min95%99.0%1016 (1.60 d)14
2. Perforated Al Core Prep2,268 s45 min90%97.2%820 (2.00 d)9
3. Autoclave Structural Bond2,916 s60 min84%94.8%1526 (2.60 d)7
4. Ti Potting Insert CNC1,998 s25 min93%97.8%513 (1.30 d)11
5. Outgassing & Flatness Test1,836 s15 min95%96.8%511 (1.10 d)13

Key figures

Takt time
2,700 s
Lead time
10.5 d
Value-added time
10,773 s
Process cycle efficiency (PCE)
3.8%
Rolled throughput yield (RTY)
86.4%
Customer demand per day
10 parts
Line capacity per day
7 parts
Bottleneck
Autoclave Structural Bond

Reading the bottleneck

The bottleneck is "Autoclave Structural Bond": it can process 7 parts per day against a demand of 10 parts, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 2,916 s to 3,662 s, against a takt of 2,700 s. The largest loss at this step is equipment downtime (uptime 84%), about 555 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.