One-Piece CFRP Aircraft Fuselage Section

Product family: Carbon Monocoque Barrels.

Flow: Carbon prepreg supplier → Rotating Mandrel AFP → Stringer Hat Co-Bond Bag → Mega-Autoclave Cure Cycle → Gantry Ultrasonic Trim → Full-Barrel Phased Array NDT → Airframe Section Join Bay

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: One-Piece CFRP Aircraft Fuselage SectionSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Carbon prepreg supplier → Rotating Mandrel AFP (13,163 s) → Stringer Hat Co-Bond Bag (17,010 s) → Mega-Autoclave Cure Cycle (21,870 s) → Gantry Ultrasonic Trim (14,985 s) → Full-Barrel Phased Array NDT (13,770 s) → Airframe Section Join Bay.SUPPLIERCarbon prepregsupplierI1.50 d1Rotating MandrelAFPC/T 13,163 sI2.00 d2Stringer HatCo-Bond BagC/T 17,010 sI2.50 d3Mega-AutoclaveCure CycleC/T 21,870 sI1.25 d4Gantry UltrasonicTrimC/T 14,985 sI1.00 d5Full-BarrelPhased Array NDTC/T 13,770 sI1.50 dCUSTOMERAirframeSection Join…4 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Rotating Mandrel AFP13,163 s20 min95%99.0%46 (1.50 d)6
2. Stringer Hat Co-Bond Bag17,010 s45 min90%97.2%38 (2.00 d)4
3. Mega-Autoclave Cure Cycle21,870 s60 min84%94.8%610 (2.50 d)3
4. Gantry Ultrasonic Trim14,985 s25 min93%97.8%25 (1.25 d)5
5. Full-Barrel Phased Array NDT13,770 s15 min95%96.8%24 (1.00 d)5

Key figures

Takt time
20,250 s
Lead time
10.7 d
Value-added time
80,798 s
Process cycle efficiency (PCE)
9.3%
Rolled throughput yield (RTY)
86.4%
Customer demand per day
4 units
Line capacity per day
3 units
Bottleneck
Mega-Autoclave Cure Cycle

Reading the bottleneck

The bottleneck is "Mega-Autoclave Cure Cycle": it can process 3 units per day against a demand of 4 units, so it falls short of demand by 28.5%. Once downtime and scrap are counted, its cycle time grows from 21,870 s to 27,464 s, against a takt of 20,250 s. The largest loss at this step is equipment downtime (uptime 84%), about 4,166 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.