Blended Aerodynamic Split-Scimitar Winglet

Product family: Drag-Reduction Tip Winglets.

Flow: High-modulus prepreg supplier → CNC Cut Kit & Debulk → Resin Film Infusion Cure → Edge Trim & Lightning Mesh → Static-Drain Wick Mount → 3D Contour Wind-Shape Scan → Wing Final Install

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Blended Aerodynamic Split-Scimitar WingletSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. High-modulus prepreg supplier → CNC Cut Kit & Debulk (1,170 s) → Resin Film Infusion Cure (1,512 s) → Edge Trim & Lightning Mesh (1,944 s) → Static-Drain Wick Mount (1,332 s) → 3D Contour Wind-Shape Scan (1,224 s) → Wing Final Install.SUPPLIERHigh-modulusprepregsupplierI1.60 d1CNC Cut Kit &DebulkC/T 1,170 sI2.00 d2Resin FilmInfusion CureC/T 1,512 sI2.60 d3Edge Trim &Lightning MeshC/T 1,944 sI1.30 d4Static-Drain WickMountC/T 1,332 sI1.10 d53D ContourWind-Shape ScanC/T 1,224 sI1.50 dCUSTOMERWing FinalInstall30 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. CNC Cut Kit & Debulk1,170 s20 min95%99.0%3048 (1.60 d)42
2. Resin Film Infusion Cure1,512 s45 min90%97.2%2460 (2.00 d)29
3. Edge Trim & Lightning Mesh1,944 s60 min84%94.8%4578 (2.60 d)21
4. Static-Drain Wick Mount1,332 s25 min93%97.8%1539 (1.30 d)35
5. 3D Contour Wind-Shape Scan1,224 s15 min95%96.8%1533 (1.10 d)39

Key figures

Takt time
1,800 s
Lead time
10.2 d
Value-added time
7,182 s
Process cycle efficiency (PCE)
1.3%
Rolled throughput yield (RTY)
86.4%
Customer demand per day
30 parts
Line capacity per day
21 parts
Bottleneck
Edge Trim & Lightning Mesh

Reading the bottleneck

The bottleneck is "Edge Trim & Lightning Mesh": it can process 21 parts per day against a demand of 30 parts, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 1,944 s to 2,441 s, against a takt of 1,800 s. The largest loss at this step is equipment downtime (uptime 84%), about 370 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Carbon Composites & Autoclave: Carbon Composites & Autoclave