Unmanned 30mm Armored Vehicle Gun Turret

Product family: Gyrostabilized IFV Turrets.

Flow: Armor steel supplier → Ballistic Plate Weld & Stress → Elevation/Traverse Ring Bore → Cannon Cradle & Loader Fit → Day/Thermal Sight Boresight → Stabilized Live-Fire Range QC → Defense Vehicle Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Unmanned 30mm Armored Vehicle Gun TurretSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Armor steel supplier → Ballistic Plate Weld & Stress (6,120 s) → Elevation/Traverse Ring Bore (7,560 s) → Cannon Cradle & Loader Fit (9,630 s) → Day/Thermal Sight Boresight (7,020 s) → Stabilized Live-Fire Range QC (5,220 s) → Defense Vehicle Line.SUPPLIERArmor steelsupplierI2.00 d1Ballistic PlateWeld & StressC/T 6,120 sI1.83 d2Elevation/TraverseRing BoreC/T 7,560 sI2.50 d3Cannon Cradle &Loader FitC/T 9,630 sI1.33 d4Day/Thermal SightBoresightC/T 7,020 sI0.83 d5StabilizedLive-Fire Range…C/T 5,220 sI1.50 dCUSTOMERDefense VehicleLine6 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Ballistic Plate Weld & Stress6,120 s35 min95%99.0%912 (2.00 d)8
2. Elevation/Traverse Ring Bore7,560 s30 min91%96.5%511 (1.83 d)6
3. Cannon Cradle & Loader Fit9,630 s45 min84%94.8%615 (2.50 d)4
4. Day/Thermal Sight Boresight7,020 s25 min92%97.6%58 (1.33 d)7
5. Stabilized Live-Fire Range QC5,220 s10 min97%99.2%25 (0.83 d)10

Key figures

Takt time
9,000 s
Lead time
10.7 d
Value-added time
35,550 s
Process cycle efficiency (PCE)
6.2%
Rolled throughput yield (RTY)
87.7%
Customer demand per day
6 units
Line capacity per day
4 units
Bottleneck
Cannon Cradle & Loader Fit

Reading the bottleneck

The bottleneck is "Cannon Cradle & Loader Fit": it can process 4 units per day against a demand of 6 units, so it falls short of demand by 29.3%. Once downtime and scrap are counted, its cycle time grows from 9,630 s to 12,093 s, against a takt of 9,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 1,834 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.