Level-IV Silicon Carbide Ballistic Armor Plate

Product family: Hot-Pressed SiC Ceramic Inserts.

Flow: SiC armor-ceramic supplier → Isostatic Hot-Press SiC Tile → Ultrasonic Tile Density Audit → UHMWPE Autoclave Laminate → Woven Nylon Edge Wrap & Seal → X-Ray & NIJ Shot Lot Test → Tactical Armor Programs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Level-IV Silicon Carbide Ballistic Armor PlateSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. SiC armor-ceramic supplier → Isostatic Hot-Press SiC Tile (82.0 s) → Ultrasonic Tile Density Audit (101 s) → UHMWPE Autoclave Laminate (128 s) → Woven Nylon Edge Wrap & Seal (94.0 s) → X-Ray & NIJ Shot Lot Test (70.0 s) → Tactical Armor Programs.SUPPLIERSiCarmor-ceramicsupplierI2.00 d1IsostaticHot-Press SiC…C/T 82.0 sI1.80 d2Ultrasonic TileDensity AuditC/T 101 sI2.50 d3UHMWPE AutoclaveLaminateC/T 128 sI1.40 d4Woven Nylon EdgeWrap & SealC/T 94.0 sI0.80 d5X-Ray & NIJ ShotLot TestC/T 70.0 sI1.50 dCUSTOMERTactical ArmorPrograms450 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Isostatic Hot-Press SiC Tile82.0 s35 min95%99.0%675900 (2.00 d)603
2. Ultrasonic Tile Density Audit101 s30 min91%96.5%360810 (1.80 d)450
3. UHMWPE Autoclave Laminate128 s45 min84%94.8%4501,125 (2.50 d)319
4. Woven Nylon Edge Wrap & Seal94.0 s25 min92%97.6%360630 (1.40 d)498
5. X-Ray & NIJ Shot Lot Test70.0 s10 min97%99.2%113360 (0.80 d)709

Key figures

Takt time
120 s
Lead time
10.0 d
Value-added time
475 s
Process cycle efficiency (PCE)
0.088%
Rolled throughput yield (RTY)
87.7%
Customer demand per day
450 parts
Line capacity per day
319 parts
Bottleneck
UHMWPE Autoclave Laminate

Reading the bottleneck

The bottleneck is "UHMWPE Autoclave Laminate": it can process 319 parts per day against a demand of 450 parts, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 128 s to 161 s, against a takt of 120 s. The largest loss at this step is equipment downtime (uptime 84%), about 24.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Defense, Naval & Optronics Systems: Defense, Naval & Optronics Systems