Level-IV Silicon Carbide Ballistic Armor Plate
Product family: Hot-Pressed SiC Ceramic Inserts.
Flow: SiC armor-ceramic supplier → Isostatic Hot-Press SiC Tile → Ultrasonic Tile Density Audit → UHMWPE Autoclave Laminate → Woven Nylon Edge Wrap & Seal → X-Ray & NIJ Shot Lot Test → Tactical Armor Programs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Isostatic Hot-Press SiC Tile | 82.0 s | 35 min | 95% | 99.0% | 675 | 900 (2.00 d) | 603 |
| 2. Ultrasonic Tile Density Audit | 101 s | 30 min | 91% | 96.5% | 360 | 810 (1.80 d) | 450 |
| 3. UHMWPE Autoclave Laminate | 128 s | 45 min | 84% | 94.8% | 450 | 1,125 (2.50 d) | 319 |
| 4. Woven Nylon Edge Wrap & Seal | 94.0 s | 25 min | 92% | 97.6% | 360 | 630 (1.40 d) | 498 |
| 5. X-Ray & NIJ Shot Lot Test | 70.0 s | 10 min | 97% | 99.2% | 113 | 360 (0.80 d) | 709 |
Key figures
- Takt time
- 120 s
- Lead time
- 10.0 d
- Value-added time
- 475 s
- Process cycle efficiency (PCE)
- 0.088%
- Rolled throughput yield (RTY)
- 87.7%
- Customer demand per day
- 450 parts
- Line capacity per day
- 319 parts
- Bottleneck
- UHMWPE Autoclave Laminate
Reading the bottleneck
The bottleneck is "UHMWPE Autoclave Laminate": it can process 319 parts per day against a demand of 450 parts, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 128 s to 161 s, against a takt of 120 s. The largest loss at this step is equipment downtime (uptime 84%), about 24.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Defense, Naval & Optronics Systems: Defense, Naval & Optronics Systems
- Submarine Acoustic Composite Bow Sonar Dome
- Unmanned 30mm Armored Vehicle Gun Turret
- VPX Conduction-Cooled Tactical Edge Server
- Airborne Multi-Spectral EOTS Targeting Pod
- Gen-3 Quad-Tube Night Vision Goggle Binocular
- 42-Meter Hollow Marine Propulsion Shaft Line
- Sub-Safe Nickel-Aluminum-Bronze Hull Valve
- Tactical Interceptor Electromechanical Fin Kit
- S-Band Naval Solid-State Phased Radar Mast
- Autonomous Unmanned Surface Patrol Craft
- MIL-STD Software-Defined Tactical Manpack