42-Meter Hollow Marine Propulsion Shaft Line
Product family: Forged Duplex Stainless Shafts.
Flow: Steel forging house → Deep Trepanning Bore 18m → CNC Turning Steady Rest → GRP Composite Protective Wrap → Ultrasonic Concentricity Check → Class-Society Sea Stamp → Frigate Shipyard Slipway
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Deep Trepanning Bore 18m | 9,180 s | 35 min | 95% | 99.0% | 6 | 8 (2.00 d) | 5 |
| 2. CNC Turning Steady Rest | 11,340 s | 30 min | 91% | 96.5% | 3 | 7 (1.75 d) | 4 |
| 3. GRP Composite Protective Wrap | 14,445 s | 45 min | 84% | 94.8% | 4 | 10 (2.50 d) | 3 |
| 4. Ultrasonic Concentricity Check | 10,530 s | 25 min | 92% | 97.6% | 3 | 6 (1.50 d) | 4 |
| 5. Class-Society Sea Stamp | 7,830 s | 10 min | 97% | 99.2% | 1 | 3 (0.75 d) | 7 |
Key figures
- Takt time
- 13,500 s
- Lead time
- 11.0 d
- Value-added time
- 53,325 s
- Process cycle efficiency (PCE)
- 9.0%
- Rolled throughput yield (RTY)
- 87.7%
- Customer demand per day
- 4 parts
- Line capacity per day
- 3 parts
- Bottleneck
- GRP Composite Protective Wrap
Reading the bottleneck
The bottleneck is "GRP Composite Protective Wrap": it can process 3 parts per day against a demand of 4 parts, so it falls short of demand by 29.3%. Once downtime and scrap are counted, its cycle time grows from 14,445 s to 18,140 s, against a takt of 13,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 2,751 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Defense, Naval & Optronics Systems: Defense, Naval & Optronics Systems
- Submarine Acoustic Composite Bow Sonar Dome
- Unmanned 30mm Armored Vehicle Gun Turret
- VPX Conduction-Cooled Tactical Edge Server
- Airborne Multi-Spectral EOTS Targeting Pod
- Gen-3 Quad-Tube Night Vision Goggle Binocular
- Level-IV Silicon Carbide Ballistic Armor Plate
- Sub-Safe Nickel-Aluminum-Bronze Hull Valve
- Tactical Interceptor Electromechanical Fin Kit
- S-Band Naval Solid-State Phased Radar Mast
- Autonomous Unmanned Surface Patrol Craft
- MIL-STD Software-Defined Tactical Manpack