Submarine Acoustic Composite Bow Sonar Dome

Product family: Hydrodynamic Acoustic Windows.

Flow: Glass-epoxy supplier → Split Mold Gelcoat & Lay → Vacuum Infusion Cure Cycle → Ti Flange Bond & Drill → Water-Tank Acoustic Loss Scan → Hydro-Pressure Fatigue Sign → Naval Submarine Yards

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Submarine Acoustic Composite Bow Sonar DomeSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Glass-epoxy supplier → Split Mold Gelcoat & Lay (6,120 s) → Vacuum Infusion Cure Cycle (7,560 s) → Ti Flange Bond & Drill (9,630 s) → Water-Tank Acoustic Loss Scan (7,020 s) → Hydro-Pressure Fatigue Sign (5,220 s) → Naval Submarine Yards.SUPPLIERGlass-epoxysupplierI2.00 d1Split MoldGelcoat & LayC/T 6,120 sI1.67 d2Vacuum InfusionCure CycleC/T 7,560 sI2.67 d3Ti Flange Bond &DrillC/T 9,630 sI1.33 d4Water-TankAcoustic Loss…C/T 7,020 sI0.67 d5Hydro-PressureFatigue SignC/T 5,220 sI1.67 dCUSTOMERNaval SubmarineYards3 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Split Mold Gelcoat & Lay6,120 s35 min95%99.0%56 (2.00 d)4
2. Vacuum Infusion Cure Cycle7,560 s30 min91%96.5%25 (1.67 d)3
3. Ti Flange Bond & Drill9,630 s45 min84%94.8%38 (2.67 d)2
4. Water-Tank Acoustic Loss Scan7,020 s25 min92%97.6%24 (1.33 d)3
5. Hydro-Pressure Fatigue Sign5,220 s10 min97%99.2%12 (0.67 d)5

Key figures

Takt time
9,000 s
Lead time
11.3 d
Value-added time
35,550 s
Process cycle efficiency (PCE)
11.6%
Rolled throughput yield (RTY)
87.7%
Customer demand per day
3 units
Line capacity per day
2 units
Bottleneck
Ti Flange Bond & Drill

Reading the bottleneck

The bottleneck is "Ti Flange Bond & Drill": it can process 2 units per day against a demand of 3 units, so it falls short of demand by 33.0%. Once downtime and scrap are counted, its cycle time grows from 9,630 s to 12,093 s, against a takt of 9,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 1,834 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Defense, Naval & Optronics Systems: Defense, Naval & Optronics Systems