Autonomous Unmanned Surface Patrol Craft

Product family: 11m Carbon/HDPE Patrol USVs.

Flow: Marine Composite Kits → Twin-Shell Hull Infusion → Foam Buoyancy & Bulkhead → Twin Jet Drive & Genset Fit → Autopilot Radar Mast Rig → Sea-Trial Autonomy Sign-Off → Coastal Defense Agencies

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Autonomous Unmanned Surface Patrol CraftSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Marine Composite Kits → Twin-Shell Hull Infusion (3,672 s) → Foam Buoyancy & Bulkhead (4,536 s) → Twin Jet Drive & Genset Fit (5,778 s) → Autopilot Radar Mast Rig (4,212 s) → Sea-Trial Autonomy Sign-Off (3,132 s) → Coastal Defense Agencies.SUPPLIERMarineComposite KitsI2.00 d1Twin-Shell HullInfusionC/T 3,672 sI1.80 d2Foam Buoyancy &BulkheadC/T 4,536 sI2.60 d3Twin Jet Drive &Genset FitC/T 5,778 sI1.40 d4Autopilot RadarMast RigC/T 4,212 sI0.80 d5Sea-TrialAutonomy Sign-OffC/T 3,132 sI1.60 dCUSTOMERCoastal DefenseAgencies5 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Twin-Shell Hull Infusion3,672 s35 min95%99.0%810 (2.00 d)7
2. Foam Buoyancy & Bulkhead4,536 s30 min91%96.5%49 (1.80 d)5
3. Twin Jet Drive & Genset Fit5,778 s45 min84%94.8%513 (2.60 d)3
4. Autopilot Radar Mast Rig4,212 s25 min92%97.6%47 (1.40 d)5
5. Sea-Trial Autonomy Sign-Off3,132 s10 min97%99.2%14 (0.80 d)8

Key figures

Takt time
5,400 s
Lead time
11.0 d
Value-added time
21,330 s
Process cycle efficiency (PCE)
7.2%
Rolled throughput yield (RTY)
87.7%
Customer demand per day
5 units
Line capacity per day
3 units
Bottleneck
Twin Jet Drive & Genset Fit

Reading the bottleneck

The bottleneck is "Twin Jet Drive & Genset Fit": it can process 3 units per day against a demand of 5 units, so it falls short of demand by 33.0%. Once downtime and scrap are counted, its cycle time grows from 5,778 s to 7,256 s, against a takt of 5,400 s. The largest loss at this step is equipment downtime (uptime 84%), about 1,101 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.