S-Band Naval Solid-State Phased Radar Mast
Product family: Shipboard Air-Defense Radars.
Flow: Phased-array module supplier → Al Alloy Structural Pedestal → T/R Module Array Backplane → Dielectric Coolant Flush → Rotary Joint RF Slip-Ring Test → Far-Field Maritime Pattern → Destroyer Integration Yard
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Al Alloy Structural Pedestal | 4,590 s | 35 min | 95% | 99.0% | 6 | 8 (2.00 d) | 5 |
| 2. T/R Module Array Backplane | 5,670 s | 30 min | 91% | 96.5% | 3 | 7 (1.75 d) | 4 |
| 3. Dielectric Coolant Flush | 7,223 s | 45 min | 84% | 94.8% | 4 | 10 (2.50 d) | 3 |
| 4. Rotary Joint RF Slip-Ring Test | 5,265 s | 25 min | 92% | 97.6% | 3 | 6 (1.50 d) | 4 |
| 5. Far-Field Maritime Pattern | 3,915 s | 10 min | 97% | 99.2% | 1 | 3 (0.75 d) | 6 |
Key figures
- Takt time
- 6,750 s
- Lead time
- 11.0 d
- Value-added time
- 26,663 s
- Process cycle efficiency (PCE)
- 9.0%
- Rolled throughput yield (RTY)
- 87.7%
- Customer demand per day
- 4 units
- Line capacity per day
- 3 units
- Bottleneck
- Dielectric Coolant Flush
Reading the bottleneck
The bottleneck is "Dielectric Coolant Flush": it can process 3 units per day against a demand of 4 units, so it falls short of demand by 33.0%. Once downtime and scrap are counted, its cycle time grows from 7,223 s to 9,070 s, against a takt of 6,750 s. The largest loss at this step is equipment downtime (uptime 84%), about 1,376 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Defense, Naval & Optronics Systems: Defense, Naval & Optronics Systems
- Submarine Acoustic Composite Bow Sonar Dome
- Unmanned 30mm Armored Vehicle Gun Turret
- VPX Conduction-Cooled Tactical Edge Server
- Airborne Multi-Spectral EOTS Targeting Pod
- Gen-3 Quad-Tube Night Vision Goggle Binocular
- Level-IV Silicon Carbide Ballistic Armor Plate
- 42-Meter Hollow Marine Propulsion Shaft Line
- Sub-Safe Nickel-Aluminum-Bronze Hull Valve
- Tactical Interceptor Electromechanical Fin Kit
- Autonomous Unmanned Surface Patrol Craft
- MIL-STD Software-Defined Tactical Manpack