Airborne Multi-Spectral EOTS Targeting Pod

Product family: MWIR + Laser Designator Pods.

Flow: Cooled infrared detector supplier → Precision Ball Gimbal Build → ZnS Infrared Optics Align → Laser Rangefinder Bore-Sight → Dry N2 Purge & Backfill → MIL Environmental & Track QC → Defense Flight Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Airborne Multi-Spectral EOTS Targeting PodSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Cooled infrared detector supplier → Precision Ball Gimbal Build (1,530 s) → ZnS Infrared Optics Align (1,890 s) → Laser Rangefinder Bore-Sight (2,408 s) → Dry N2 Purge & Backfill (1,755 s) → MIL Environmental & Track QC (1,305 s) → Defense Flight Line.SUPPLIERCooled infrareddetectorsupplierI2.00 d1Precision BallGimbal BuildC/T 1,530 sI1.83 d2ZnS InfraredOptics AlignC/T 1,890 sI2.50 d3Laser RangefinderBore-SightC/T 2,408 sI1.42 d4Dry N2 Purge &BackfillC/T 1,755 sI0.83 d5MIL Environmental& Track QCC/T 1,305 sI1.50 dCUSTOMERDefense FlightLine12 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Precision Ball Gimbal Build1,530 s35 min95%99.0%1824 (2.00 d)16
2. ZnS Infrared Optics Align1,890 s30 min91%96.5%1022 (1.83 d)12
3. Laser Rangefinder Bore-Sight2,408 s45 min84%94.8%1230 (2.50 d)8
4. Dry N2 Purge & Backfill1,755 s25 min92%97.6%1017 (1.42 d)13
5. MIL Environmental & Track QC1,305 s10 min97%99.2%310 (0.83 d)18

Key figures

Takt time
2,250 s
Lead time
10.4 d
Value-added time
8,888 s
Process cycle efficiency (PCE)
3.2%
Rolled throughput yield (RTY)
87.7%
Customer demand per day
12 units
Line capacity per day
8 units
Bottleneck
Laser Rangefinder Bore-Sight

Reading the bottleneck

The bottleneck is "Laser Rangefinder Bore-Sight": it can process 8 units per day against a demand of 12 units, so it falls short of demand by 33.0%. Once downtime and scrap are counted, its cycle time grows from 2,408 s to 3,024 s, against a takt of 2,250 s. The largest loss at this step is equipment downtime (uptime 84%), about 459 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.