Powder-Metallurgy Nickel HPC Rotor Disk

Product family: PM Nickel-Superalloy Compressor Disks.

Flow: Forged disc supplier → Ultrasonic Shear Immersion → CNC Lathe Rough & Stress-Rel → Broach 64 Fir-Tree Dovetails → Shot-Peen Rim & Barkhausen → CMM Pitch & Spin Overspeed → Core Engine Assembly

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Powder-Metallurgy Nickel HPC Rotor DiskSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Forged disc supplier → Ultrasonic Shear Immersion (2,430 s) → CNC Lathe Rough & Stress-Rel (2,835 s) → Broach 64 Fir-Tree Dovetails (3,645 s) → Shot-Peen Rim & Barkhausen (2,565 s) → CMM Pitch & Spin Overspeed (2,194 s) → Core Engine Assembly.SUPPLIERForged discsupplierI2.50 d1Ultrasonic ShearImmersionC/T 2,430 sI2.19 d2CNC Lathe Rough &Stress-RelC/T 2,835 sI2.63 d3Broach 64Fir-Tree…C/T 3,645 sI1.38 d4Shot-Peen Rim &BarkhausenC/T 2,565 sI1.13 d5CMM Pitch & SpinOverspeedC/T 2,194 sI1.50 dCUSTOMERCore EngineAssembly16 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Ultrasonic Shear Immersion2,430 s40 min92%96.4%3240 (2.50 d)19
2. CNC Lathe Rough & Stress-Rel2,835 s50 min89%97.1%1635 (2.19 d)16
3. Broach 64 Fir-Tree Dovetails3,645 s65 min83%94.2%1642 (2.63 d)11
4. Shot-Peen Rim & Barkhausen2,565 s30 min92%98.0%822 (1.38 d)18
5. CMM Pitch & Spin Overspeed2,194 s45 min94%98.8%818 (1.13 d)21

Key figures

Takt time
3,375 s
Lead time
11.6 d
Value-added time
13,669 s
Process cycle efficiency (PCE)
2.2%
Rolled throughput yield (RTY)
85.4%
Customer demand per day
16 parts
Line capacity per day
11 parts
Bottleneck
Broach 64 Fir-Tree Dovetails

Reading the bottleneck

The bottleneck is "Broach 64 Fir-Tree Dovetails": it can process 11 parts per day against a demand of 16 parts, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 3,645 s to 4,662 s, against a takt of 3,375 s. The largest loss at this step is equipment downtime (uptime 83%), about 747 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.