Lobed Chevron Acoustic Jet Exhaust Mixer

Product family: Noise-Reducing Titanium Mixers.

Flow: Ti-15-3-3-3 Sheet → Superplastic Hot-Form Press → Laser Trim & Lobe Tack → Vacuum Chamber TIG Weld → Radiographic Seam Inspect → Acoustic Flange Datum Mill → Engine Exhaust Nozzle Bay

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Lobed Chevron Acoustic Jet Exhaust MixerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Ti-15-3-3-3 Sheet → Superplastic Hot-Form Press (2,777 s) → Laser Trim & Lobe Tack (3,240 s) → Vacuum Chamber TIG Weld (4,166 s) → Radiographic Seam Inspect (2,931 s) → Acoustic Flange Datum Mill (2,507 s) → Engine Exhaust Nozzle Bay.SUPPLIERTi-15-3-3-3SheetI2.50 d1SuperplasticHot-Form PressC/T 2,777 sI2.21 d2Laser Trim & LobeTackC/T 3,240 sI2.57 d3Vacuum ChamberTIG WeldC/T 4,166 sI1.43 d4Radiographic SeamInspectC/T 2,931 sI1.07 d5Acoustic FlangeDatum MillC/T 2,507 sI1.50 dCUSTOMEREngine ExhaustNozzle Bay14 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Superplastic Hot-Form Press2,777 s40 min92%96.4%2835 (2.50 d)17
2. Laser Trim & Lobe Tack3,240 s50 min89%97.1%1431 (2.21 d)14
3. Vacuum Chamber TIG Weld4,166 s65 min83%94.2%1436 (2.57 d)9
4. Radiographic Seam Inspect2,931 s30 min92%98.0%720 (1.43 d)16
5. Acoustic Flange Datum Mill2,507 s45 min94%98.8%715 (1.07 d)18

Key figures

Takt time
3,857 s
Lead time
11.6 d
Value-added time
15,621 s
Process cycle efficiency (PCE)
2.5%
Rolled throughput yield (RTY)
85.4%
Customer demand per day
14 units
Line capacity per day
9 units
Bottleneck
Vacuum Chamber TIG Weld

Reading the bottleneck

The bottleneck is "Vacuum Chamber TIG Weld": it can process 9 units per day against a demand of 14 units, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 4,166 s to 5,328 s, against a takt of 3,857 s. The largest loss at this step is equipment downtime (uptime 83%), about 853 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.