Laser-Drilled Effusion Cooling Combustor

Product family: Low-NOx Annular Combustors.

Flow: Cobalt-nickel superalloy supplier → Hydro-Spin Annular Shell → 5000-Hole Laser Effusion Drill → Electron-Beam Flange Weld → Yttria TBC Thermal Spray → Flow-Check Pressure Drop Map → Turbofan Hot Core Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Laser-Drilled Effusion Cooling CombustorSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Cobalt-nickel superalloy supplier → Hydro-Spin Annular Shell (2,777 s) → 5000-Hole Laser Effusion Drill (3,240 s) → Electron-Beam Flange Weld (4,166 s) → Yttria TBC Thermal Spray (2,931 s) → Flow-Check Pressure Drop Map (2,507 s) → Turbofan Hot Core Line.SUPPLIERCobalt-nickelsuperalloysupplierI2.50 d1Hydro-SpinAnnular ShellC/T 2,777 sI2.21 d25000-Hole LaserEffusion DrillC/T 3,240 sI2.57 d3Electron-BeamFlange WeldC/T 4,166 sI1.43 d4Yttria TBCThermal SprayC/T 2,931 sI1.07 d5Flow-CheckPressure Drop MapC/T 2,507 sI1.50 dCUSTOMERTurbofan HotCore Line14 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Hydro-Spin Annular Shell2,777 s40 min92%96.4%2835 (2.50 d)17
2. 5000-Hole Laser Effusion Drill3,240 s50 min89%97.1%1431 (2.21 d)14
3. Electron-Beam Flange Weld4,166 s65 min83%94.2%1436 (2.57 d)9
4. Yttria TBC Thermal Spray2,931 s30 min92%98.0%720 (1.43 d)16
5. Flow-Check Pressure Drop Map2,507 s45 min94%98.8%715 (1.07 d)18

Key figures

Takt time
3,857 s
Lead time
11.6 d
Value-added time
15,621 s
Process cycle efficiency (PCE)
2.5%
Rolled throughput yield (RTY)
85.4%
Customer demand per day
14 units
Line capacity per day
9 units
Bottleneck
Electron-Beam Flange Weld

Reading the bottleneck

The bottleneck is "Electron-Beam Flange Weld": it can process 9 units per day against a demand of 14 units, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 4,166 s to 5,328 s, against a takt of 3,857 s. The largest loss at this step is equipment downtime (uptime 83%), about 853 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.