High-Bypass Geared Turbofan Final Line
Product family: Complete Commercial Jet Engines.
Flow: Tier-1 Fan, Core & LPT Modules → Core-to-Fan Gearbox Mate → LPT Shaft Tensioning → External Harness & Tube Dress → FADEC Rig & Trim Balance → Sea-Level Full-Thrust Run → Airframer wing-mount line
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Core-to-Fan Gearbox Mate | 6,480 s | 40 min | 92% | 96.4% | 12 | 15 (2.50 d) | 7 |
| 2. LPT Shaft Tensioning | 7,560 s | 50 min | 89% | 97.1% | 6 | 13 (2.17 d) | 6 |
| 3. External Harness & Tube Dress | 9,720 s | 65 min | 83% | 94.2% | 6 | 16 (2.67 d) | 4 |
| 4. FADEC Rig & Trim Balance | 6,840 s | 30 min | 92% | 98.0% | 3 | 8 (1.33 d) | 7 |
| 5. Sea-Level Full-Thrust Run | 5,850 s | 45 min | 94% | 98.8% | 3 | 7 (1.17 d) | 8 |
Key figures
- Takt time
- 9,000 s
- Lead time
- 12.0 d
- Value-added time
- 36,450 s
- Process cycle efficiency (PCE)
- 5.6%
- Rolled throughput yield (RTY)
- 85.4%
- Customer demand per day
- 6 units
- Line capacity per day
- 4 units
- Bottleneck
- External Harness & Tube Dress
Reading the bottleneck
The bottleneck is "External Harness & Tube Dress": it can process 4 units per day against a demand of 6 units, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 9,720 s to 12,432 s, against a takt of 9,000 s. The largest loss at this step is equipment downtime (uptime 83%), about 1,991 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Jet Engines & Propulsion Systems: Jet Engines & Propulsion Systems
- Single-Crystal Nickel-Superalloy Turbine Blade Cast
- Powder-Metallurgy Nickel HPC Rotor Disk
- Laser-Drilled Effusion Cooling Combustor
- Cooled Nozzle Guide Vane Stator Sector
- Composite Fan Cowl & Exhaust Nacelle Build
- 150kW Aircraft Auxiliary Power Unit Assembly
- Liquid Hydrogen Cryogenic Rocket Valve
- LOX / Methane Rocket Engine Turbopump
- Ceramic Silicon-Nitride Mainshaft Engine Bearing
- Additive-Printed Titanium Engine Fuel Nozzle
- Lobed Chevron Acoustic Jet Exhaust Mixer