Single-Crystal Nickel-Superalloy Turbine Blade Cast
Product family: Hollow High-Pressure Blades.
Flow: Single-crystal casting foundry → Ceramic Core & Wax Inject → Robotic Slurry Shell Dip → Bridgman Single-Crystal Cast → Laue X-Ray Crystal Check → EDM Film-Cool & Thermal Coat → High-Pressure Turbine Module
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Ceramic Core & Wax Inject | 324 s | 40 min | 92% | 96.4% | 360 | 450 (2.50 d) | 218 |
| 2. Robotic Slurry Shell Dip | 378 s | 50 min | 89% | 97.1% | 180 | 396 (2.20 d) | 178 |
| 3. Bridgman Single-Crystal Cast | 486 s | 65 min | 83% | 94.2% | 180 | 468 (2.60 d) | 124 |
| 4. Laue X-Ray Crystal Check | 342 s | 30 min | 92% | 98.0% | 90 | 252 (1.40 d) | 204 |
| 5. EDM Film-Cool & Thermal Coat | 293 s | 45 min | 94% | 98.8% | 90 | 198 (1.10 d) | 240 |
Key figures
- Takt time
- 450 s
- Lead time
- 11.3 d
- Value-added time
- 1,823 s
- Process cycle efficiency (PCE)
- 0.20%
- Rolled throughput yield (RTY)
- 85.4%
- Customer demand per day
- 180 parts
- Line capacity per day
- 124 parts
- Bottleneck
- Bridgman Single-Crystal Cast
Reading the bottleneck
The bottleneck is "Bridgman Single-Crystal Cast": it can process 124 parts per day against a demand of 180 parts, so it falls short of demand by 31.1%. Once downtime and scrap are counted, its cycle time grows from 486 s to 622 s, against a takt of 450 s. The largest loss at this step is equipment downtime (uptime 83%), about 99.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Jet Engines & Propulsion Systems: Jet Engines & Propulsion Systems
- Powder-Metallurgy Nickel HPC Rotor Disk
- Laser-Drilled Effusion Cooling Combustor
- Cooled Nozzle Guide Vane Stator Sector
- Composite Fan Cowl & Exhaust Nacelle Build
- 150kW Aircraft Auxiliary Power Unit Assembly
- High-Bypass Geared Turbofan Final Line
- Liquid Hydrogen Cryogenic Rocket Valve
- LOX / Methane Rocket Engine Turbopump
- Ceramic Silicon-Nitride Mainshaft Engine Bearing
- Additive-Printed Titanium Engine Fuel Nozzle
- Lobed Chevron Acoustic Jet Exhaust Mixer