Fly-by-Wire Titanium Hydraulic Manifold

Product family: Primary Flight Control Blocks.

Flow: Titanium bar stock supplier → Cross-Hole Deep Drilling → EDM Micro-Orifice Valve → Thermal Deburr & Micro-Hone → Hard-Coat Valve Sleeve Fit → 6000-PSI Impulse Decay → Flight Control Actuation

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Fly-by-Wire Titanium Hydraulic ManifoldSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Titanium bar stock supplier → Cross-Hole Deep Drilling (720 s) → EDM Micro-Orifice Valve (936 s) → Thermal Deburr & Micro-Hone (1,296 s) → Hard-Coat Valve Sleeve Fit (984 s) → 6000-PSI Impulse Decay (840 s) → Flight Control Actuation.SUPPLIERTitanium barstock supplierI2.20 d1Cross-Hole DeepDrillingC/T 720 sI2.40 d2EDM Micro-OrificeValveC/T 936 sI2.80 d3Thermal Deburr &Micro-HoneC/T 1,296 sI2.20 d4Hard-Coat ValveSleeve FitC/T 984 sI1.20 d56000-PSI ImpulseDecayC/T 840 sI1.80 dCUSTOMERFlight ControlActuation45 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Cross-Hole Deep Drilling720 s25 min96%99.4%9099 (2.20 d)71
2. EDM Micro-Orifice Valve936 s35 min92%98.5%68108 (2.40 d)51
3. Thermal Deburr & Micro-Hone1,296 s85 min83%95.0%45126 (2.80 d)30
4. Hard-Coat Valve Sleeve Fit984 s30 min93%98.2%6899 (2.20 d)49
5. 6000-PSI Impulse Decay840 s15 min95%97.6%2354 (1.20 d)58

Key figures

Takt time
1,200 s
Lead time
12.7 d
Value-added time
4,776 s
Process cycle efficiency (PCE)
0.70%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
45 parts
Line capacity per day
30 parts
Bottleneck
Thermal Deburr & Micro-Hone

Reading the bottleneck

The bottleneck is "Thermal Deburr & Micro-Hone": it can process 30 parts per day against a demand of 45 parts, so it falls short of demand by 33.9%. Once downtime and scrap are counted, its cycle time grows from 1,296 s to 1,644 s, against a takt of 1,200 s. The largest loss at this step is equipment downtime (uptime 83%), about 265 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of 5-Axis Aerospace Machining & NDT: 5-Axis Aerospace Machining & NDT