7075-T6 Aluminum Monolithic Wing Rib Line

Product family: Machined Aircraft Wing Ribs.

Flow: Aluminum plate mill → Vacuum Table Datum Skim → High-Speed Pocket Hog-Out → Flip-Side Web Thin Wall → Chromic Anodize & Prime → Automated Articulated CMM → Wing Box Assembly Bay

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 7075-T6 Aluminum Monolithic Wing Rib LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aluminum plate mill → Vacuum Table Datum Skim (498 s) → High-Speed Pocket Hog-Out (648 s) → Flip-Side Web Thin Wall (897 s) → Chromic Anodize & Prime (681 s) → Automated Articulated CMM (582 s) → Wing Box Assembly Bay.SUPPLIERAluminum platemillI2.20 d1Vacuum TableDatum SkimC/T 498 sI2.40 d2High-Speed PocketHog-OutC/T 648 sI2.80 d3Flip-Side WebThin WallC/T 897 sI2.20 d4Chromic Anodize &PrimeC/T 681 sI1.20 d5AutomatedArticulated CMMC/T 582 sI1.80 dCUSTOMERWing BoxAssembly Bay65 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Vacuum Table Datum Skim498 s25 min96%99.4%130143 (2.20 d)102
2. High-Speed Pocket Hog-Out648 s35 min92%98.5%98156 (2.40 d)74
3. Flip-Side Web Thin Wall897 s85 min83%95.0%65182 (2.80 d)43
4. Chromic Anodize & Prime681 s30 min93%98.2%98143 (2.20 d)71
5. Automated Articulated CMM582 s15 min95%97.6%3378 (1.20 d)83

Key figures

Takt time
831 s
Lead time
12.7 d
Value-added time
3,306 s
Process cycle efficiency (PCE)
0.48%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
65 parts
Line capacity per day
43 parts
Bottleneck
Flip-Side Web Thin Wall

Reading the bottleneck

The bottleneck is "Flip-Side Web Thin Wall": it can process 43 parts per day against a demand of 65 parts, so it falls short of demand by 33.9%. Once downtime and scrap are counted, its cycle time grows from 897 s to 1,138 s, against a takt of 831 s. The largest loss at this step is equipment downtime (uptime 83%), about 184 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of 5-Axis Aerospace Machining & NDT: 5-Axis Aerospace Machining & NDT