Ultra-High-Strength 300M Landing Gear Piston
Product family: Main Gear Shock Struts.
Flow: Landing-gear forging house → Gun-Drill Deep Bore → CNC Contour Turn & Mill → Vacuum Carburize & Quench → HVOF Carbide Thermal Spray → Mag-Particle & Bore Gage → Landing System Integrators
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Gun-Drill Deep Bore | 2,314 s | 25 min | 96% | 99.4% | 28 | 31 (2.21 d) | 22 |
| 2. CNC Contour Turn & Mill | 3,009 s | 35 min | 92% | 98.5% | 21 | 34 (2.43 d) | 16 |
| 3. Vacuum Carburize & Quench | 4,166 s | 85 min | 83% | 95.0% | 14 | 39 (2.79 d) | 9 |
| 4. HVOF Carbide Thermal Spray | 3,163 s | 30 min | 93% | 98.2% | 21 | 31 (2.21 d) | 15 |
| 5. Mag-Particle & Bore Gage | 2,700 s | 15 min | 95% | 97.6% | 7 | 17 (1.21 d) | 18 |
Key figures
- Takt time
- 3,857 s
- Lead time
- 12.9 d
- Value-added time
- 15,352 s
- Process cycle efficiency (PCE)
- 2.2%
- Rolled throughput yield (RTY)
- 89.1%
- Customer demand per day
- 14 parts
- Line capacity per day
- 9 parts
- Bottleneck
- Vacuum Carburize & Quench
Reading the bottleneck
The bottleneck is "Vacuum Carburize & Quench": it can process 9 parts per day against a demand of 14 parts, so it falls short of demand by 33.9%. Once downtime and scrap are counted, its cycle time grows from 4,166 s to 5,283 s, against a takt of 3,857 s. The largest loss at this step is equipment downtime (uptime 83%), about 853 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of 5-Axis Aerospace Machining & NDT: 5-Axis Aerospace Machining & NDT
- Aerospace 5-Axis CNC & NDT Inspection
- Titanium Compressor Blisk 5-Axis Flank Mill
- 7075-T6 Aluminum Monolithic Wing Rib Line
- 30-Meter Long-Bed Wing Spar Milling
- Accessory Drive Gearbox Magnesium Casting
- Fly-by-Wire Titanium Hydraulic Manifold
- 15-5PH Stainless Flap Track Carriage
- Main Rotor Helicopter Swashplate Assembly
- Nickel-Alloy 718 Satellite Thruster Chamber
- Ti-5553 Engine Mount Pylon Drag Fitting
- 7150 Aluminum Extruded Cabin Seat Track