15-5PH Stainless Flap Track Carriage

Product family: Wing High-Lift Mechanisms.

Flow: Stainless forging supplier → CNC Datum Slab Milling → Bore & Gear Rack Broach → H1025 Precipitation Harden → Cadmium/Zn-Ni Corrosion Coat → Load Bearing Fit & NDT → Wing Trailing Edge Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 15-5PH Stainless Flap Track CarriageSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Stainless forging supplier → CNC Datum Slab Milling (900 s) → Bore & Gear Rack Broach (1,170 s) → H1025 Precipitation Harden (1,620 s) → Cadmium/Zn-Ni Corrosion Coat (1,230 s) → Load Bearing Fit & NDT (1,050 s) → Wing Trailing Edge Line.SUPPLIERStainlessforgingsupplierI2.19 d1CNC Datum SlabMillingC/T 900 sI2.39 d2Bore & Gear RackBroachC/T 1,170 sI2.81 d3H1025Precipitation…C/T 1,620 sI2.19 d4Cadmium/Zn-NiCorrosion CoatC/T 1,230 sI1.19 d5Load Bearing Fit& NDTC/T 1,050 sI1.81 dCUSTOMERWing TrailingEdge Line36 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. CNC Datum Slab Milling900 s25 min96%99.4%7279 (2.19 d)56
2. Bore & Gear Rack Broach1,170 s35 min92%98.5%5486 (2.39 d)41
3. H1025 Precipitation Harden1,620 s85 min83%95.0%36101 (2.81 d)24
4. Cadmium/Zn-Ni Corrosion Coat1,230 s30 min93%98.2%5479 (2.19 d)39
5. Load Bearing Fit & NDT1,050 s15 min95%97.6%1843 (1.19 d)46

Key figures

Takt time
1,500 s
Lead time
12.7 d
Value-added time
5,970 s
Process cycle efficiency (PCE)
0.87%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
36 parts
Line capacity per day
24 parts
Bottleneck
H1025 Precipitation Harden

Reading the bottleneck

The bottleneck is "H1025 Precipitation Harden": it can process 24 parts per day against a demand of 36 parts, so it falls short of demand by 33.9%. Once downtime and scrap are counted, its cycle time grows from 1,620 s to 2,055 s, against a takt of 1,500 s. The largest loss at this step is equipment downtime (uptime 83%), about 332 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.